How to Prepare a BOQ for Dismantling and Demolition Works?

Preamble for the Dismantling Work Bill of Quantity

The rate for all demolishing and dismantling to include carting and disposing of the debris outside the site at approved State/Municipal Dumping grounds as per Project Manager's instruction. Necessary propping, shoring, and/or underpinning shall be provided for the safety of the adjoining work or property, which is to be left intact, before dismantling and demolishing is taken up, and the work shall be carried out in such a way that no damage is caused to the adjoining work or property. While dismantling plumbing & sanitary fittings & pipeline, in case any builder-related connection/fixture gets affected, the same will be replaced by the Contractor free of cost. The bidder should engage a skilled team to isolate the live services prior to starting dismantling. The necessary protection process should cover under the dismantling vendor's scope. Temporary partition and one-side finishing can be under the dismantling vendor's scope. The rate for all demolishing and dismantling to include carting and disposing of the debris outside the site at approved State/Municipal Dumping grounds as per Project Manager's instructions.

Key Considerations for BOQ in Dismantling & Demolition Works



How to Prepare a BOQ for Demolition of Existing Granite/Tile Hard Flooring

Demolition of Granite/Tile Hard Flooring Including Mortar, Screeding, and PCC

Demolition of the existing granite/tile (all types) hard flooring including mortar, screeding/PCC below & carrying the debris away from the site as per architects/PM instruction. Cost to include chipping of the existing floor once the hard floor is removed to make the floor level, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Demolition of Existing Wall Tiles

Demolition of Wall Tiles and Proper Disposal

Demolition of existing wall tiles & carrying the debris away from the site, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Demolition of Gypsum, Grid, Designer, and Baffle Ceilings

Demolition of Gypsum/Grid/Designer/Baffle Ceilings Including Scaffolding

Demolition of the existing gypsum/grid ceiling/designer ceiling/all types of baffle ceiling & carrying the debris away from the site as per architects/PM instruction. Cost to include scaffolding & other works involved to remove the ceiling, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Demolition of Gypsum/Ply Partitions, Tables, Service Counters, and Storage Units

Demolition of Gypsum/Ply Partitions and Furniture

Demolition of the existing gypsum/ply partitions, tables, service counter, storage, and above-ceiling partitions & carrying the debris away from the site as per architects/PM instruction, etc., complete and as directed by the "Engineer-in-Charge/Architect".


How to Prepare a BOQ for Scrubbing, Grinding, and Removing Existing Wall Paneling/Wallpaper

Scrubbing and Removing Wall Paneling/Wallpaper

Existing wall paneling/wallpaper scrubbing, grinding, removing & carrying the debris away from the site as per architects/PM instruction, etc., complete and as directed by the "Engineer-in-Charge/Architect".


How to Prepare a BOQ for Demolition of Existing Glass Partitions Including Doors

Demolition of Glass Partitions and Doors

Demolition of existing glass partitions including doors and above-ceiling partitions & carrying the debris away from the site, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Removal of Existing Granite/Marble Cladding

Demolition of Granite/Marble Cladding

Demolition of existing granite/marble cladding & carrying the debris away from the site, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Demolition of Existing Block Walls

Demolition of Block Walls Including Plaster, Paint, and Doors

Demolition of the existing block wall (all sizes) including plaster, paint, tile dado, doors, skirting & carrying the debris away from the site, etc., complete and as directed by Engineer-in-Charge/Architect.


How to Prepare a BOQ for Scrubbing, Grinding, and Removing Ply/Laminate Doors

Scrubbing and Removing Ply/Laminate Doors

Existing door ply/laminate scrubbing, grinding, removing & carrying the debris away from the site as per architects/PM instruction, etc., complete and as directed by the "Engineer-in-Charge/Architect".


How to Prepare a BOQ for Removal and Reinstallation of Existing Doors

Removal and Reinstallation of Fire/Flush/Glass/PVC Doors

Removing of existing fire/flush/glass door/PVC without damages and handing over the same with all the removed accessories, and to reinstall the door if required as directed by "Engineer-in-Charge/Architect".
a. Single leaf door
b. Double leaf door


How to Prepare a BOQ for Removal of Existing Carpet Floor Tiles

Removal of Carpet Floor Tiles Including Adhesive Base

Removing of existing carpet floor tile including base adhesive without damages and handing over the serviceable items to the Client and disposing of the unserviceable materials/debris and carting away from the site, etc., complete and as directed.


How to Prepare a BOQ for Relaying Existing Carpet Flooring

Relaying Carpet Flooring with Protection

Relaying of existing carpet neatly, complete and as directed. Rate includes a single layer of protection cover to be laid after installation of carpet, etc., complete and as directed.


How to Prepare a BOQ for Deep Cleaning Existing Carpet

Deep Cleaning Carpet Using Shampooing Method

Deep cleaning the existing carpet floor by shampooing method and drying the same neatly, complete and as directed.


How to Prepare a BOQ for Refixing Flush/Fire/Glass Doors

Refixing of Flush/Fire/Glass Doors with Accessories

Refixing of flush/fire/glass door and hardware with minimum accessories like anchor bolts, screws, etc., complete and as directed by the "Engineer-in-Charge/Architect".
a. Single leaf door
b. Double leaf door


How to Prepare a BOQ for Dismantling Existing Electrical Works

Dismantling of Electrical Works Based on Site Survey

Dismantling of existing electrical works, etc., complete and as directed by the "Engineer-in-Charge/Architect". (Vendor to quote as per the site survey)


How to Prepare a BOQ for Dismantling Existing HVAC Works

Dismantling of HVAC Works Based on Site Survey

Dismantling of existing HVAC works, etc., complete and as directed by the "Engineer-in-Charge/Architect". (Vendor to quote as per the site survey)


How to Prepare a BOQ for Dismantling Fire Alarm and Public Address Systems

Dismantling of Fire Alarm System (FAS) and Public Address (PA) Systems

Dismantling of existing FAS, PA works, etc., complete and as directed by the "Engineer-in-Charge/Architect". (Vendor to quote as per the site survey)


How to Prepare a BOQ for Dismantling Plumbing and Sanitary Works

Dismantling of PHE Works Including Restroom Cubicles and Drainage Lines

Dismantling of existing PHE works not limited to existing restroom cubicles, sanitary fittings, plumbing supply & drain line, etc., complete and as directed by the "Engineer-in-Charge/Architect". (Vendor to quote as per the site survey)


How to Prepare a BOQ for Groove Cutting and Dismantling Grano

Groove Cutting and Dismantling Grano as per Raceway Marking

Groove cutting and dismantling the existing Grano as per the raceways marking and removing the debris, etc., complete complying with standard specifications and as directed by the "Engineer-in-Charge/Architect".


How to Prepare a BOQ for Removing Existing Blinds

Removal of Blinds While Retaining Serviceable Items

Removing existing blinds, etc., without damages and handing over the serviceable items to the Client and disposing of the unserviceable materials/debris and carting away from the site, etc., complete and as directed by the "Engineer-in-Charge/Architect".


How to Prepare a BOQ for Dismantling Raised Floor Systems

Dismantling and Handling Raised Floor Systems

Dismantling of existing raised floor system, etc., without damages and handing over the serviceable items to the Client and disposing of the unserviceable materials/debris and carting away from the site, etc., complete and as directed by the "Engineer-in-Charge/Architect".


Conclusion

This guide provides a detailed framework for preparing a Bill of Quantities (BOQ) for various demolition and dismantling works, ensuring compliance with project requirements and proper disposal of debris as per the Engineer-in-Charge or Architect’s instructions.

 