Here is a detailed table that will cover the details for footing design for the project manager as well as the civil engineers so that footing sizes and requirements can be established effectively.
Category |
Checklist Item |
Details & Considerations |
Standard Guidelines & Codes |
Thumb Rule for Quick Estimation |
1.
Load Considerations |
Dead
Load |
Weight
of the structure (columns, beams, slabs, walls, finishes). |
IS 875
Part 1 |
1
kN/m² for normal RCC floors |
|
Live
Load |
Load
from occupants, furniture, and temporary loads. |
IS 875
Part 2 |
2-5
kN/m² for residential & commercial buildings |
|
Wind
Load |
Important
for high-rise structures & open areas. |
IS 875
Part 3 |
Consider
if building height > 10m |
|
Seismic
Load |
Required
in earthquake zones. |
IS
1893:2016 |
Zone
II & above: Use ductile detailing |
|
Impact
Load |
Load
from heavy machinery, elevators, etc. |
IS 875
Part 5 |
Not
needed for normal residential structures |
2.
Soil Investigation |
Soil
Bearing Capacity (SBC) |
Determines
footing size and depth. |
IS
6403:1981 |
SBC ≥
150 kN/m² for normal footings |
|
Soil
Type |
Clay,
sand, rock, and their impact on foundation stability. |
Geotechnical
Report |
Stronger
soil = Smaller footings |
|
Water
Table Level |
High
water tables require waterproofing. |
Site
Investigation |
If
water table is high, use raft/pile foundation |
3.
Footing Type Selection |
Isolated
Footing |
For
single columns, cost-effective, requires good SBC. |
IS
456:2000 |
Use if
column spacing > 3m |
|
Combined
Footing |
Supports
two or more columns when they are closely spaced. |
IS
456:2000 |
Use if
spacing < 3m |
|
Raft/Mat
Foundation |
Used
for weak soil conditions. |
IS
2950:1981 |
Use if
SBC < 100 kN/m² |
|
Pile
Foundation |
Used
for deep foundations where soil has low bearing capacity. |
IS
2911:2010 |
Use if
SBC < 50 kN/m² |
|
Strip
Footing |
Used
for walls or closely spaced columns. |
RCC
& Structural Design |
Width
= 2 × wall thickness |
4.
Footing Dimensions |
Footing
Depth (Df) |
Minimum
1.2m below ground level or per soil conditions. |
IS
456:2000 |
Df =
1.5 × column width |
|
Footing
Area (A) |
A =
Load on Column / SBC |
Structural
Design |
A =
1.5 × column area |
|
Footing
Thickness (D) |
Minimum
150mm–200mm for isolated footings. |
Thumb
Rule: D = Load/1000 |
D =
1/10th of column height |
|
Pedestal
Size |
Width
≥ Column Width + 100 mm |
Structural
Requirements |
Pedestal
width = 1.5 × column width |
|
Footing
Projection (P) |
Min. 150mm
– 300mm beyond column size. |
As per
IS Standards |
P =
0.3 × footing width |
5.
Reinforcement Details |
Minimum
Steel Percentage |
0.12%
- 0.3% of the total concrete volume. |
IS
456:2000 |
0.15%
of total volume for isolated footings |
|
Rebar
Size |
Generally
12mm to 25mm diameter bars used. |
Site
Requirements |
12mm
for light loads, 16mm+ for heavy loads |
|
Rebar
Spacing |
Typically
150mm – 200mm center-to-center. |
Standard
RCC Design |
Spacing
= 3 × bar diameter |
|
Development
Length (Ld) |
Ensures
proper anchorage of reinforcement. |
IS
456:2000 |
Ld =
50 × bar diameter |
|
Lap
Length |
For
bars >12mm, lap length = 50d (d = bar dia). |
IS
456:2000 |
Lap =
40 × bar dia (tension), 50 × bar dia (compression) |
6.
Structural Stability Considerations |
Moment
& Shear Forces |
Footings
must resist shear forces and bending moments. |
Structural
Load Analysis |
Check
for punching shear if column is slender |
|
One-Way
Shear Check |
Vu ≤
Ï„_c bd (Shear Capacity Check). |
IS
456:2000 |
Shear
stress ≤ 0.25 × concrete strength |
|
Two-Way
Shear (Punching Shear) |
Vu ≤
1.5Ï„_c bo d (Critical in isolated footings). |
IS
456:2000 |
Increase
depth if punching shear > limit |
|
Differential
Settlement Control |
Limit
differential settlement to avoid structural cracking. |
As per
Site Conditions |
ΔSettlement
≤ 25mm for residential buildings |
7.
Additional Considerations |
Concrete
Grade |
Min. M20
for RCC footing (M25 or higher for high loads). |
IS
456:2000 |
Concrete
Strength (MPa) = Load / Footing Area |
|
Curing
Period |
14 –
28 days for maximum strength. |
Standard
RCC Practice |
Minimum
7 days if using rapid hardening cement |
|
Waterproofing
& Drainage |
Necessary
for footings in high water table areas. |
IS
3370:2009 |
Provide
100mm PCC under footing if required |
|
Formwork
Removal Time |
Min. 7
days for footing sides. |
As per
IS 456:2000 |
Side
forms: 2 days; Bottom forms: 7 days |
Key Takeaways for Project Managers
✔
Correct footing design assures structural stability and durability.
✔
Load calculations and soil investigations are essential for footing
selection.
✔ IS
codes and geotechnical reports avoid foundation failures in the
future.
✔ For durability,
sufficient reinforcement and quality of concrete have to be ensured.
No comments:
Post a Comment