Air Handling Units play a very critical role in an HVAC system because they regulate the quality of air and maintain conditions indoors. For efficient operation, safety compliance, and integration with fire control systems, the installation of an AHU needs to be precise. This check list will give the project manager a step-by-step approach to verify all the necessary parameters during the installation of an AHU, from fire panel integration to damper integration.
Category |
Checklist Item |
Specification / What to Verify |
Status (✔/✘/N/A) |
Remarks |
1. Pre-Installation |
Approved
AHU layout and drawings received? |
Check
approved layout, duct routing, and coordination with fire & electrical
systems. |
|
|
|
Site
readiness confirmed? |
Ensure AHU
placement is accessible, flooring supports are ready, and required clearance
is available. |
|
|
|
AHU
delivery verified? |
Match model
number, airflow capacity (CFM), external static pressure (Pa), and motor
specifications with BOQ. |
|
|
|
Fire panel
and BMS interface drawings reviewed? |
Ensure
control wiring layout for fire panel integration and BMS monitoring is
available. |
|
|
|
Lifting
and handling clearance checked? |
Verify
space for safe unloading, movement, and installation of AHU. |
|
|
2.
Mounting & Positioning |
Proper
leveling and alignment? |
AHU should
be level to ±3mm, check with a spirit level, ensure correct orientation. |
|
|
|
Vibration
isolators installed? |
Install
anti-vibration mounts/spring isolators as per manufacturer guidelines. |
|
|
|
Drain pan
slope verified? |
Minimum 1:100
slope towards the drain outlet, check with a water test. |
|
|
|
Access
panel clearance? |
Ensure at
least 600mm clearance for filter, fan, and coil maintenance. |
|
|
3. Duct
& Piping Connections |
Supply
& return duct alignment? |
Match to
AHU flange, ensure flexible duct connectors at fan discharge and intake. |
|
|
|
Duct
insulation and sealing? |
Use
approved insulation (min. 25mm thick) and seal joints with duct sealant or
tape. |
|
|
|
Fire
damper installed and integrated? |
Confirm placement
at duct penetration, check actuator wiring to fire panel. |
|
|
|
Chilled
water/DX piping verified? |
Pipe size,
insulation thickness (min. 13mm Nitrile rubber for chilled water), correct
valve placement. |
|
|
|
Condensate
drain line tested? |
Drain pipe
slope 1:50, confirm no leaks, install U-trap if required. |
|
|
4. Fire
Panel & Damper Integration |
Fire
damper actuator function tested? |
Simulate
fire alarm to check auto-closure and status feedback to fire panel. |
|
|
|
AHU auto
shut-off tested via fire panel? |
Verify AHU
stops operation when smoke detector triggers fire alarm. |
|
|
|
Smoke
detector installed inside AHU? |
Check
placement near return air intake, confirm functionality. |
|
|
|
Fire alarm
interface connected to BMS? |
Ensure
proper signal transmission for alarm and status monitoring. |
|
|
|
Emergency
manual override tested? |
Verify
emergency shutdown and manual damper release functions. |
|
|
5.
Electrical & Controls |
Power
supply and voltage checked? |
Verify voltage
(415V/3Ph/50Hz), ensure correct phase sequence and power rating. |
|
|
|
Motor
wiring, earthing verified? |
Ensure
secure terminations, proper earthing (≤ 5Ω), check MCCB rating. |
|
|
|
BMS/control
panel connected? |
Check
wiring for airflow sensors, temperature sensors, damper control. |
|
|
|
AHU
interlocks with exhaust fans tested? |
Verify
sequencing logic for fresh air and exhaust system synchronization. |
|
|
6.
Testing & Commissioning |
AHU
operational test performed? |
Ensure
smooth startup, measure current draw, check for unusual noise/vibrations. |
|
|
|
Airflow
and static pressure verified? |
Measure
airflow (CFM) and external static pressure (Pa), match design values. |
|
|
|
Noise and
vibration levels acceptable? |
Ensure within
manufacturer-specified decibel levels. |
|
|
|
Fire panel
integration test completed? |
Perform
full fire safety simulation with AHU response verification. |
|
|
|
Filters
installed and checked? |
Confirm
filter type (HEPA, MERV rating), ensure proper sealing, record initial
pressure drop. |
|
|
|
Final
commissioning report prepared? |
Document
airflow readings, damper operation, fire integration test, and approvals. |
|
|
Conclusion
Installation of AHU installation checklist ensures the smooth operation while ensuring fire
safety integration. Such a checklist makes it possible to avoid common pitfalls,
enhance the compliance with safety aspects, and build a
reliable system.
For further insights into HVAC installations, keep reading our
blog!
No comments:
Post a Comment