As soon as
the project's scope is reasonably defined – the next two key aspects of the
project that the Project Manager must focus on are an assessment of Cost
and Time.
Larger
projects may have a specialist consultant to assist with the development and
management of the Project Budget and Project Schedule but on smaller projects,
this is rarely the case. And even on larger projects, the PM will need to
develop an early appraisal of time and cost before they can access specialist
advice.
Project
Deliverables, Work Breakdown Structure and Milestone Program
A project
manager needs to know how to develop a milestone program and a project budget
from the first principles this assist immensely in getting an early grasp on a
projects scale and mapping out early requirements. This skill also assists the
project manager in the future when they get to review and assess timelines and
budget generated by others.
Budgeting
and scheduling from the first principles are both informed by the process of
decomposition – the breaking down of a project, applying a traditional
waterfall methodology, so that each project deliverable is identified and
broken down into lower levels of activity in outline format. This reduces the
project into its component deliverables and activities and into a table format
known as work breakdown structures or WBS.
The WBS is then quantified (each activity valued against time and cost). If the activity being down even further. Once assessed each individual value can be aggregated to build an overall appraisal of time and cost. In the absence of any other historical data this process will be the most accurate way a project manager has to create a project manager has to create as project schedule and a project budget. Thid detailed breakdown is the best way for a project manager to really get to know the project. I will also assist the project manager identify resourcing needs and isolate elements of risk.
Bottom-up
Estimating
Bottom-up
estimating is a method that involves estimating the individual cost and likely
time taken for each activity or deliverable identified in the WBS and then
assembling all these estimates into an aggregated estimate of time and cost for
the entire project.
In the early
stages of a project such estimation may provide only a rough order of cost but
as the project progresses and is better understood – greater accuracy can be
expected. It may also be that the WBS makes it possible for the Project Manager
to apply prior knowledge or experience to valuing certain activities. This will
likely add to the accuracy of the estimate.
While cost
estimating is a relatively linear process with all the costs aggregating into
an overall final estimate it is not the same for estimating the project
timeline. This is because some activities can and may overlap – Therefore the
Project Manager needs to be able to identify parallel activities and moderate
the project time to accommodate overlaps and to allow for periods of waiting
that may be inherent between activities.
Example
of a WBS that includes Time & $$$ estimates
The Pros
and Cons of Bottom-up Estimating
PROS
·
Bottom-up
estimates can be very accurate especially when the project team responsible for
their particular component gets to put a time and cost value against it.
·
Estimation
errors tend to balance out across the components of a project. If the time or
cost of one work package has been underestimated, this will likely be offset by
an overestimation of another work package.
·
Bottom-up
estimating can be enhanced by other statistical/historical inputs where
available.
·
This
method can also be used to assess time and cost impacts of proposed changes.
CONS
·
The
aggregated project estimate may fail to identify project-specific additional or
overhead costs – this is especially true on larger more complex projects – eg.
where a tower crane may be an added whole of project cost.
·
Bottom-up
estimation requires a lot more effort to develop and can be seen as tedious and
more onerous than a simple $ per m2 estimate.
·
It’s
impossible to apply without a proper WBS.
·
Estimation
errors will likely lead to both inaccurate time and cost estimates.
·
Bottom-up
estimates are still at risk to the bias or inexperience of the estimators. The
only document what they know or are familiar with.
The Project
Management Plan is the lead document in a project director’s suite of
controls.
As a
minimum, it should answer the basic four questions.
- What is the work to be performed
- Why is it being sponsored
- Who is involved and what are
their responsibilities
- When is the work to be done
A
well-developed Project Plan will address all 10 PMBOK Knowledge Areas.
Early effort
by the Project Manager to develop a WBS to analyse the project’s deliverables
in detail will directly address three of these 10 knowledge areas – Time , Cost
and Resources. The WBS will provide also useful intelligence to inform the
project’s risk profile and procurement requirements.
No comments:
Post a Comment