Testing and Commissioning in LV Panels Construction | Low Voltage Panels - teamlceted - LCETED - LCETED Institute for Civil Engineers

Post Top Ad

Apr 21, 2023

Testing and Commissioning in LV Panels Construction | Low Voltage Panels - teamlceted

Testing and Commissioning in LV Panels Construction Works |LV Panels Package Factory Acceptance testing (FAT) | LV Panels Package Site Acceptance testing (SAT) | LV Panels Package Test Reports in Excel Sheet | LV Panels Package List of Tests | Low Voltage Panels Testing and Commissioning Requirement Compliance Sheet | Low Voltage Panels Systems List of Tests

 

In this article, we have listed out Types of FFS (Fire Fighting System) Package Testing and Commissioning on factories and Sites for construction works and Test Instrumentation Required/Considered for Site Acceptance Testing (SAT)

 

Following are the Low Voltage Panels Systems that shall be carried out in construction works


T&C Requirement Compliance Sheet Required for LV Panels

1. "Physical inspection and specs. Verification – Verification has to be done with approved GA drawing, SLD, BOQ, and method statements."

 

2. First Megger (Before High Voltage test)

 

3. High voltage dielectric test - 2.5kV for 01min.

 

4. Second Megger (Post High Voltage test)

 

5. Torque test - During FAT all the joint sections on the horizontal & vertical bus bars are to be verified with a torque wrench and to be marked for tightness. During SAT all input/output terminations and busbar joint sections are to be verified with a torque wrench. Note: The torque values table shall be provided by the panel manufacturer.

 

6. "Mili Volt Drop Test - For the panels transported to the site in isolated sections, post alignment of such panels onsite horizontal joint sections to be verified using mili volt drop test kit"

 

7. Control Circuit Verification Test

 

8. CT Test: - Polarity & Ratio to be verify.

 

9. Measuring Instruments: Parameter to be verified by connecting available load.

 

10. Switchgears Mechanical / Electrical Operation & Voltage Verification

 

11. Verification of interlocks (Mechanical / Electrical)

 

12. "Primary injection test for all Breakers - During FAT this test is to be done on the rated value of the breaker and during SAT, this test is to be done on the set values as per discrimination study."

 

13. Secondary injection test for Micrologic breakers - During FAT this test is to be done and during SAT, this test is to be done on the set values as per the discrimination study.

 

14. Verification of BMS interface points

Testing and Commissioning in LV Panels Construction


Test Instrumentation Required/Considered for LV Panels Site Acceptance Testing (SAT)

1. 3-Phase Power Quality Analyzer

2. True RMS Multi-meter

3. True RMS Clamp meter

4. Insulation resistance tester (0-1000V)

5. Phase sequence meter

6. Digital thermographic scanner

7. Hi-post test kit (2.5 kV)

8. Primary injection kit set

9. Secondary injection kit set

10. Torque Wrench

11. Test Lamp Kit

12. Millivolt drop test kit


Testing and Commissioning in LV Panels Construction


NOTE: Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT)


CLICK TO DOWNLOAD EXCEL SHEET

Low Voltage Panels



No comments:

Post a Comment

LCETED - "WHATSAPP GROUP"

For Instant updates Join our Whatsapp Group. Save our Whatsapp contact +919840140396 as LCETED and Send us a message “JOIN”

Post Bottom Ad