Testing and Commissioning in HVAC Construction Works | HVAC Package Factory Acceptance testing (FAT) | HVAC Package Site Acceptance testing (SAT) | HVAC Package Test Reports in Excel Sheet | HVAC Package List of Tests | HVAC Package Testing and Commissioning Requirement Compliance Sheet | HVAC Systems List of Tests
In this article, we
have listed out Types of HVAC Package Testing and Commissioning on factories
and Sites for construction works and Test Instrumentation
Required/Considered for Site Acceptance Testing (SAT)
Following is the HVAC
Package that shall be carried out on construction works
HVAC Package - CHW AHU
1. Physical
inspection and specs. Verification
2. Duct Pressure
test
3. Chilled water
coil pressure test
4. Condensate drain
line slope test
5. Air CFM
Measurement
6. Air Balancing
verification
7. Duct static
pressure verification
8. Alarm & Fire
interlocking verification
9. Modulation valve
operation verification
10. Heat Load test
@ Design Load
11. Noise Level
Verification
12. Vibration check
13. AHU VFD Panel
VFD Modulation & Panel Operation verification
14. CHW Water
Balancing
15. BMS integration
verification
16. Dampers
Operation Verification
17. Heat Recovery
Unit Operation Verification
18. CHW line
Pressure test & Chemical Flushing
19. AHU Filters
Verification
HVAC Package - VAV Boxes
1. Installation
Verification
2. VAV box
calibration verification as per design
3. BMS integration
verification
HVAC Package - EXHAUST & FRESH AIR FANS
1. Physical
inspection and specs. Verification
2. Duct pressure
test
3. Fan Functional
Verification (CFM & Electrical Parameter)
4. Fan Static
measurement
5. Fan Auto/manual
& Fire Integration verification
6. Air Balancing
verification
7. Alarm & Fire
interlocking verification
8. Noise level
Verification
9. Vibration level
verification
10. BMS integration
verification
HVAC Package - VRF System
1. Physical
inspection and specs. Verification
2. Copper pipe
pressure test
3. Unit vacuum test
4. Unit startup and
verification of alarms
5. Air CFM
Measurement
6. Air Balancing
verification
7. Display Control
Panel & Operations Checks
8. "Performance
test, Heat rejection & COP Calculation & Verification.
100% sensible
design load of unit/room capacity to be placed 24 hrs. during SAT with 12 Hrs.
changeover between working and standby unit. Temperature data loggers shall hang
at different locations as per drawing to log the T + Rh for 24 hrs. during the heat
run test. Measure the parameters of Airside & Electrical for indoor &
outdoor units."
9. "Drain Pump
- Drain Line leakage/slope check and Drain Pump operation to be
verify."
10. Sequential
Timer Panel Verification (if any): Units logic Operations & Verifications
11. Alarm &
Fire interlocking verification
12. BMS integration
verification
13. Noise level
Verification
Test Instrumentation Required/Considered For SAT
Following is the
Test Instrumentation Required/Considered for Site Acceptance Testing (SAT) of the HVAC
Package
1. "Heater
load (for Critical Rooms HLT)
As per the heat load
calculation sheet"
2. True RMS Multi-meters
3. True RMS Clamp
meter
4. Digital
Thermometer
5. Velocity Matrix
6. Digital T+ RH
Data loggers
7. Sling Psychrometer
8. Sound level db.
meter
9. Digital Vacuum
Gauge
10. Insulation
Resistance tester
11. Air Capture
Hood
12. Duct Pressure
test kit
13. Vibration Meter
CLICK TO DOWNLOAD
EXCEL SHEET
No comments:
Post a Comment