In this article, we have listed out Types of BMS (Building Management Systems) Package Testing and Commissioning on factories and Sites for construction works and Test Instrumentation Required/Considered for Site Acceptance Testing (SAT)
Following
are the Building Management Systems that shall be carried out in construction
works
T&C Requirement Compliance Sheet
Required for Building Management System
1.
Physical inspection and specs. Verification - This has to be carried out as per
the pre-Cx check sheet given in the commissioning plan/method statement.
2.
I/O summary verification - Each point must be verified as per the approved I/O
summary.
3.
Graphic verification
- System graphics for each system are to be verified as per approved graphics
4.
Graphic status & alarm verification with filed devices - Each status on the
graphic must be verified with respect to field status. The alarm pop-up page, real-time alarm, alarm history logging, etc. must be verified.
5.
Graphic values verification with filed values - All graphic values has
to be calibrated and verified as per the field values.
Test
Instrumentation Required/Considered for Building Management System Site
Acceptance Testing (SAT)
1.
True RMS Multi-meter - 1 No.
2.
True RMS Clamp meter - 1 No.
3.
Temporary UPS for Pre-Commissioning - 1 No.
NOTE: Factory
Acceptance Testing (FAT) and Site Acceptance Testing (SAT)
CLICK TO DOWNLOAD EXCEL SHEET