Testing and Commissioning in Gas Suppression System (GSS) Package Construction Works| Gas Suppression System (GSS) Package Factory Acceptance testing (FAT) | Gas Suppression System (GSS) Package Site Acceptance testing (SAT) | Gas Suppression System (GSS) Package Test Reports in Excel Sheet | Gas Suppression System (GSS) Package Testing and Commissioning Requirement Compliance Sheet | Gas Suppression System (GSS) Package List of Tests
In this article, we have listed out Types of Gas
Suppression System (GSS) Package Testing and Commissioning on factories and
Sites for construction works and Test Instrumentation Required/Considered for
Site Acceptance Testing (SAT)
Following are the Building Management Systems that
shall be carried out in construction works
T&C
Requirement Compliance Sheet Required for Gas Suppression System (GSS) Package
1.
Physical inspection and specs. Verification - This has to
be carried out as per the pre-Cx check sheet given in the commissioning
plan/method statement.
2.
Nitrogen Pressure Test - Post installation of piping
works, a Pressure test must be done as per the commissioning plan/method statement.
3.
Room Integrity test - Post completion of all civil works
and installation of all other services room must be positively & negatively
pressurized and tested with room integrity test equipment setup. Leakage should
not be observed more than the calculated permissible leakage as per O&M.
4.
Verification of GSS system Smoke detector - The smoke detection
system has to be checked as per the designed logic or Cause & effect
matrix.
5.
Verification of Abort switch / Manual Release Switch
- While verifying this switch ensure the solenoid actuator is kept disconnected
from the cylinders.
6.
Integration of Solenoid Actuators & smoke detection system
- While verifying the integration of Solenoid actuators and the smoke detection
system, the actuator must be kept disconnected from cylinders. Verify the
programming as per Cause & effect matrix.
7.
Integration of GSS Fire Panel with Main Fire Panel and BMS system
- Verify any Alarm or fault on the GSS fire panel to be indicated on the Main Fire
Panel. Verify the monitoring of GSS in the BMS system as per the I/O summary.
Test
Instrumentation Required/Considered for Gas Suppression System (GSS) Package
Site Acceptance Testing (SAT)
1.
True RMS Multi-meter - 1 No.
2.
Pressure Gauges - 1 No.
3.
Room Integrated Test kit - 1 No.
4.
Aerosol Spray - 1 No.
NOTE: Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT)
CLICK TO DOWNLOAD EXCEL SHEET
noted with thanks.
ReplyDeleteFire protection services work with hospitals to ensure they have robust fire evacuation plans.
ReplyDeleteFire Suppression Systems
In Bangladesh, there is a broad selection of engine oils, encompassing mineral, semi-synthetic, and synthetic types, each available in different grades. This diversity allows vehicle owners to choose the right oil for their specific requirements and driving conditions. Look at this web-site Bike Engine Oil in BD.
ReplyDelete