Quality Inspection Checklist for Firefighting Works | Building Inspection Checklist for Fire and General Safety | Inspection Checklist Fire Protection Equipment
In this article, we have discussed and enclosed the quality Inspection checklist for firefighting Works (FFS) in construction to be used by civil engineers
Quality
Inspection Checklist on Installation of Fire Extinguisher
Before Installation
1. Are the fire extinguishers delivered to the site
of the required make and type?
2. Is the pressure level in the extinguishers as per
the specifications?
3. Have the locations for installation of Fire
extinguishers been identified as per drawings
After Installation
1. Travel distance to the nearest unit not exceeding
23 meters (per IRI).
2. Enough 10C rated units provided where charged
electrical equipment will be installed
3. Is the testing and commissioning of the system complete?
Quality
Inspection Checklist on Pressure Testing of Pipes
Before Installation
1. Mark the length of the pipe under test on a relevant
drawing, with the date and time of the test.
2. Ensure all the open ends have been plugged in before
starting the test. A pneumatic pressure test (at low pressure) may be
conducted.
3. Ensure all the isolation valves are closed and
locked
4. Ensure the pressurization pump is removed and the
feed valve is locked after reaching the test pressure.
a. Test pressure
b. Duration:
From:
To:
c. Visual check for the leakages
d. Observations at the end of the test
Quality
Inspection Checklist on Installation of Sprinkler
Before Installation - Ensure only a qualified welder is working on the job.
1. Check the piping is done as per the approved shop
drawing.
2. The pipe diameter, type of fittings is as per
spec.
3. All the pipe joints below 50mm diameter shall be
threaded type only.
4. The bottom-of-pipe levels are as per the coordinated
services drawing / shop drawing.
5. Pipe support is provided as per spec. Minimum at
every 2.5 meters. The support shall hang the pipes stress-free.
6. Ensure only approved welding electrodes had been
used.
7. Radiographic test to be done randomly on welded
joints. Attach test report.
8. Visual inspection of welded joints for neatness.
9. Pressure testing is to be done before painting the
pipe
10. Approved primer and paint are uniformly applied.
No coats as per spec. Apply touch-up paint wherever necessary.
11. Tapping for sprinkler drops is taken from the top
of the branch header (in case of FM-approved piping only)
12. All sprinkler drops are exactly centered with
the grid tiles. Ensure that a template is used.
13. Ensure valves are provided at the correct locations
14. Provision for draining the pipeline is done. A
pressure gauge, a ball valve, and a flexible PVC pipe to the nearest drain point
shall be provided. The same shall be removed after the successful commissioning of
the system.
15. Installed test sprinkler at a convenient location
for inspection by the Fire Authority.
16. While fixing the sprinkler heads ensure a container is kept under the sprinkler location to receive any residual water remaining inside the pipe during testing.
No comments:
Post a Comment