Steps to Effectively Kick-start Construction
Projects | How to Start a Construction Project | What Is Construction Planning?
| How to construction & Interior fit-out project step by step?
Most
people think that the initial construction kickstart is the most challenging part
of construction work. However, it takes a lot of coordination, foresight, and
analysis to get started and plan before you even get off the ground. However,
if you follow all the proper steps listed below, you can make your construction
project as painless as possible.
To
start a construction project, you will need to:
1.
Submit or collect Statutory Documents
2. Design
Part - Work on the drawings and data
3. Work
on the budget | Preparation of BOQ with the client inputs.
4. Nominate
Direct or Sub-Contractor
5. Building
Permits | Make copies of your permits.
6. Prepare the Project schedule
7. Prepare
HSE/Safety Plan.
8. Make
WSM on QA/QC Requirement Construction Plans.
9. Arrange
Temporary Facilities
10.
Procure the materials.
11.
Collect billing Supporting documents.
Statutory
Documents to submit or collect
Statutory documents to submit or collect from
our side are listed below
a. Contractual Requirements
b. Manpower Requirement
c. Temporary Facilities
d. QA/QC Requirement
e. Municipal Permits and NOCs
f. Procurement
g. Drawings and Data
h. Nominated/Direct Sub-Contractor
i. Health, Safety and Environment
To know more Read the Statutory Documents Required Construction Project
start-up | C&I Project Start-Up Checklist
Design
Part - Work on the drawings and data
Familiarize
yourself with the scope of work before starting a construction project. You
should collect all the GFC Drawings and schematics and look at them in design
detail, checking for any mistakes, problem areas, or unfamiliar markings to
rise RFI (Request for information)
If
there are no floor plans or GFC drawings, need to hire an architect and MEP
consultant or request one through your client. After the design part closure, we
need to analyze the drawing and make notes on security risks, Design
confusion, finishes schedule used & MEP requirements, and materials used on the
finishes. Raise questions for clarification to the architect and consultant on
design discussions meetings
Also
Read: How
to select Architect for the project as a Project manager?
Data
to collect you need to collect on design discussion
·
GFC Drawings
·
RCP layout
·
MEP drawings
·
Finish schedule
·
Make list
Work on
the budget | Preparation of BOQ with the client inputs.
Based on the inputs, Drawings & Scope of the work,
we need to prepare BOQ under the budget of the client or its scope of requirements.
Usually, the estimating the budget you will need to calculate the budget for
yourself, but if not, you should consider:
1.
Labor costs (contractors,
supervisors, and stakeholders – architect, consultants
& OEM consultants)
2.
Material costs
3.
Equipment and tool
costs
4.
Land Development
Costs
5.
Transportation Costs
6.
Security enforcement
and insurance costs – Car policy, EFPFO….
When setting the budget, you should consult with
professional engineers, architects, design consultants, and all your
stakeholders. Ask everyone what they think is needed to complete the project
and add % costs.
Always Plan and calculate unexpected expenses by
adding % to the budget. You should never underestimate the cost of a
construction project! Using software to analyze cost. After fixing your
budget for the project seek for the contractors to give a quote as per your BOQ
abstract sheet and finalize the team as per your requirements Which is explained
below in detail
Use the Below sheets to prepare your BOQ Abstract for your
project
Summary Sheet Format
C&I Line Items
MEP Line Items
Nominate Direct or Sub-Contractor
At this point, the contractor can send out a request for
bids to give you plenty of time to respond. To hire a contractor, you need to
provide plans, an initial budget, and more information about the project. Once
you request bids, contractors will send you the expected terms and costs of the
job, so you can accept the most competitive rates.
What are the Steps Involved
in Bidding?
1. Package strategy
Finalization – Type of contract, Project duration
(on 1st Pitch), Project Billing details, Packages in project &
Client packages (if any), Design requirements – Shop dwg
2. Vendor Pool Screening
& Finalization
3. Issuance of tender
4. Pre-Bid Meeting
5. Bid Submission by
consultant/Vendors (Pre-bid response)
6. Bid Opening &
Sign-Off
7. Bid Assessment
·
Technical assessment
& meeting
·
Commercial
negotiation & assessment
·
Compliance
assessments
8. Final Techno-Commercial
discussion
9. Final Vendor
Recommendation
10. Appointment of
consultant/Vendor
11. LOA/Purchase Order
Release
12. Award of work
13. Regret Note
Also read: How Does Construction Bidding Work? And Its Selection
Methods
Depending on the scope of your project and the
contractors you want, you may want to use a specific contract format. Always,
check every detail before signing anything. Make sure you and your contractor
understand what the plan is before legally binding your relationship.
Building
Permits | Make copies of your permits.
A work permit is a written form used to authorize jobs that
endanger workers to serious hazards. It recognizes the work to be done, the
hazards involved, and the necessary preparation and precautions for the job.
Examples of jobs needing work permits are those requiring employees to enter
and work in confined spaces, repair, maintain, or inspect electrical
installations, or use large or complex equipment.
A work permit is a written form used to authorize work that
poses serious hazards to workers. It recognizes the work to be done, the
hazards involved, and the preparation and precautions required for the work.
Examples of jobs that require a work permit include those that require
employees to enter and work in confined spaces, repair, maintain, or inspect electrical
installations or use large or complex equipment.
For more information Read: What Is a Work Permit? Types of Work permit used in
Construction work | LCETED
Prepare
Project schedule
The construction project schedule consists of the duration
of construction of various components of the work. Based on the availability of
the following data, the construction schedule can be made:
(i) Number of activities
(ii) Quantity of various
items of works
(iii) Labor contribution
and number of field workers
(iv) Machinery required
(v) Stages of activities to
be executed
For more details on Various
scheduling procedure read: Construction Scheduling Procedures | Construction
Scheduling Techniques | Details | Types
Prepare
HSE/Safety Plan.
An HSE plan to focus on the health, safety, and environmental
policies, procedures, and processes of your company and project. The goal of the
HSE/safety is to create a consistent and reliable framework that you can apply
to all your projects to improve project outcomes.
The impacts on health, safety, and the environment are
critical to the success of the project. The health and safety of your workers
must be the priority, while your management of the environment will also have a
direct impact on the course of your projects and the sustainability and viability
of your company.
An HSE plan helps companies to think consciously about
their HSE approach and then make changes and adjust the plan based on what is
happening on site. Approaching the HSE to build in this way ensures that you are
continually improving and iterating on your HSE practices.
HSE plans come in many shapes and sizes, but most are
component plans that cover environmental and health, and safety management
elements or activities.
The Article below should be part of your health and
security delivery strategy, HSE/Safety Plan for Construction, HSSE Requirements, and Site Setup Requirements
Make WSM
on QA/QC Requirement Construction Plans
Quality assurance (QA) and quality control (QC) are
critical components of any construction project. It helps to ensure that our
project meets all requirements and that any defects are identified and
corrected before they cause serious problems.
The main goal of the QA/QC program is to ensure that
the project should complete meeting all customer requirements specified in
the contract documents, and WSM Submitted, and to avoid potential problems that
could cause delays on the project timeline and cost
To obtain these goals We need to record the inspection
with a quality checklist, test data, Reporting defects, MIR, and document
corrections based on WSM
Arrange
Temporary Facilities
Before
work begins on a construction site, be it a large or small project, many
services must be temporarily set up. This is in addition to permanent services
required for complete development and temporary site facilities required for
the welfare of workers.
Creating
temporary site services should be part of site layout plans. These are prepared
by the contractors as part of their mobilization activities prior to the commencement of work on site. The below list is some of the temporary
facilities required before starting construction projects
1.
Temporary Lighting facilities
2. Site
Office – Table, Container office or temporary partition room, Fan, power supply
3. Temporary
DB board with industrial
sockets
4. Water
Supply
5. Temporary
restroom for Laborer’s and Engineers
6. CCTV
Camera
7. Covid
Protocols
8.
HSE posters
Also Read: Various
Steps in The Construction of a Residential Building
Procure
the materials.
Procurement
is a term that describes the process of purchasing goods and services. In
building construction, materials procurement is the process of selecting,
ordering, invoicing, paying, and delivering to the site materials required for
building construction. The goals of material procurement are said to be to
purchase the best product at the right quality, quantity, time, and price.
Collect
billing Supporting documents.
The
most common construction billing methods. Three main billing options in the
construction industry include Advanced Billing: Billing before the project
begins. Billing Balance: Billing at the end of the project. Progress Billing:
Billing as the project progresses.
The
following are the supporting documents for billing (Example)
1.
MIR - Material Inspection Report
2. Work
Progress Report
3.
JMR – Joint Measurement Record
4. ESI
5. PF
statement
6. Invoice
Bill
property classified ADs
ReplyDeleteDiscussing inclines, there are necessities that should be thought of and just a roofer comprehends these. Roofing
ReplyDeleteOn the off chance that your staircase has twists, corners or half-arrivals, you'll require a bended stairlift. http://www.accuratestairs.ca/
ReplyDelete"Roof repair is a smart investment to protect your home's interior." Roofing Contractor
ReplyDeleteCheck the latest price of all cars model 2023 and also compare your favourite with other because it help you in purchasing.
ReplyDelete