How to Prepare HSE/Safety Plan for Construction | HSSE Requirements | Site Setup Requirements | Checklist And Permits Frequency to follow on site
In this article, we have attached HSSE requirements, Site set-up requirements, Checklist and permits required, and frequency with other implementations that need to adhere to at the site for safety precautions.
HSSE REQUIREMENTS
1. Dedicated HSSE personal deployment.
2. Site-specific PSP – project safety plan
3. HSSE policy
4. Project Risk Assessment (HIRA) - Site Specific (COVID-19 Precautions need to incorporate)
5. SWMS - For All Works (COVID 19 Precautions need to
incorporate)
6. Logistic plan – site-specific
7. PPE Matrix
8. EVAC Insinuation plan (Floor) and ERP plan
9. HSSE training matrix – Including Third party training
10. Waste Management plan
Description |
Responsibility |
Target Date |
Dedicated HSSE personal deployment. |
|
|
Site-specific PSP – project safety plan |
|
|
HSSE policy |
|
|
Project Risk Assessment (HIRA) - Site
Specific (COVID-19 Precautions need to incorporate) |
|
|
SWMS - For All Works (COVID 19
Precautions need to incorporate) |
|
|
Logistic plan – site-specific |
|
|
PPE Matrix |
|
|
EVAC Insinuation plan (Floor) and ERP
plan |
|
|
HSSE training matrix – Including Third
party training |
|
|
Waste Management Plan |
|
|
SITE SETUP REQUIREMENTS
1. HSSE Checklist needs to be filled
2. Nearest Hospital tie up letter 24X7
3. Emergency contact numbers display with the designation.
4. HSSE Notice board and Safety Park
5. HSSE Statistics Board
6. ID cards for workers
7. Visitor induction card and visitor entry register
8. First Aid Box – First Aid Qualified members
9. HSSE Job specific posters (3/2 Standard Size – CW
& Client LOGO SHOULD BE INCLUDED
11. Fire extinguisher Min 15 points and 3 fire stands
(DCP & CO2)
12. IP Standard temporary power DB – Earthing should be
ensured
13. Double-insulated armored cables only use for power
tapping
14. Aluminum Mobile scaffold only allowed inside the
premises & Daily Inspection and record maintaining
15. “A” Type ladders are not at all allowed from the
initial stage of the project works.
16. Segregation of wastages
17. Implementation of work permits
18. MSDS display at site
19. Medical certificates for workers and staff
20. Designated area for Lunch for workers
21. Statutory Documents updates
WCP
CAR
LABOUR
LICENSE
ISMW
ESI &
PF – Registration Copy
ESI &
PF – Challan Copy
22. Deployment of B certificate electrician at site
23. Drinking water facility at the floor
24. Worker’s toilets need to be identified and
deployment of the cleaning team
25. Openable window closing/Façade protection
26. Exhaust & Industrial fan for air ventilation
Description |
Responsibility |
Target Date |
HSSE Checklist need to be filled |
|
|
Nearest Hospital tie up letter 24X7 |
|
|
Emergency contact numbers display with designation. |
|
|
HSSE Notice board and Safety Park |
|
|
HSSE Statistics board |
|
|
ID card for workers |
|
|
Visitor induction card and visitor entry register |
|
|
First Aid Box – First Aid Qualified members |
|
|
HSSE Job specific posters (3/2 Standard Size – CW
& Client LOGO SHOULD BE INCLUDED |
|
|
Fire extinguisher Min 15 points and 3 fire stands
(DCP & CO2) |
|
|
IP Standard temporary power DB – Earthing should be
ensured |
|
|
Double insulated armored cables only use for power
tapping |
|
|
Aluminum Mobile scaffold only allowed inside the
premises & Daily Inspection and record maintaining |
|
|
“A” Type ladders are not at all allowed from the
initial stage of the project works. |
|
|
Segregation of wastages |
|
|
Implementation of work permits |
|
|
MSDS display at site |
|
|
Medical certificates for workers and staff |
|
|
Designated area for Lunch for workers |
|
|
Statutory Documents updates |
|
|
WCP |
|
|
CAR |
|
|
LABOUR LICENSE |
|
|
ISMW |
|
|
ESI & PF – Registration Copy |
|
|
ESI & PF – Challan Copy |
|
|
Deployment of B certificate electrician at site |
|
|
Drinking water facility at floor – |
|
|
Worker’s toilets need to be identified and
deployment of cleaning team |
|
|
Openable window closing/Façade protection |
|
|
Exhaust & Industrial fan for air ventilation |
|
|
CHECKLIST
AND PERMIT FREQUENCY
1. Accident Incident Report Format - As and when
required
2. HSSE Statics weekly & Monthly - Once in a month
1st to 2nd & Every Friday
3. A Type ladder – Checklist - Once in a week
4. Checklist for ELCB
- Once in a month
5. Fire extinguisher checklist - Once in a Week
6. Full body harness checklist - Once in a Week
7. Gas cutting set checklist - Once in a week
8. Height work Checklist - Daily
9. Mobile scaffold Checklist & Tagging - Once in a
week
10. Power tool Checklist & Tagging - Once in a week
11. PPE Checklist - Once in a week
12. Welding Machine checklist & Tagging - Once in a
week
13. Confined Space Entry Permit - As and when required
14. General Work Permit -
Daily
15. Height Work Permit - Daily
16. Hot Work Permit
- Daily
17. Night Work Permit - Daily
18. Medical Fitness form - All new workers & Staff
19. Safety Induction Record Format - All new workers & staff
20. JST - Attendance Sheet - Once in a week
21. TBT - Daily
Description |
Frequency |
Remarks |
Accident Incident Report Format |
As and when required |
|
HSSE Statics weekly & Monthly |
Once in a month 1st to 2nd & Every Friday |
|
A Type ladder – Checklist |
Once in a week |
|
Checklist for ELCB |
Once in a month |
|
Fire extinguisher checklist |
Once in a Week |
|
Full body harness checklist |
Once in a Week |
|
Gas cutting set checklist |
Once in a week |
|
Height work Checklist |
Daily |
Before commencement of work |
Mobile scaffold Checklist & Tagging |
Once in a week |
|
Power tool Checklist & Tagging |
Once in a week |
|
PPE Checklist |
Once in a week |
|
Welding Machine checklist & Tagging |
Once in a week |
|
Confined Space Entry Permit |
As and when required |
|
General Work Permit |
Daily |
Before the commencement of work |
Height Work Permit |
Daily |
Before the commencement of work |
Hot Work Permit |
Daily |
Before the commencement of work |
Night Work Permit |
Daily |
Before the commencement of work |
Medical Fitness form |
All new workers & Staff |
|