Foundations are one of the most stressed components of concrete elements because they support and withstand the entire building. Footing should be inspected to ensure that the quality is good enough to support the weight on it.
Before the concrete is poured, a thorough inspection of the foundation should be carried out to ensure compliance with the floor plans. It's a good idea to have a checklist before the foundation inspection to avoid repairs that delay completion.
Below You can find the foundation/Footing stage Checklist for civil engineers
1. Soil Load Tests, Specified or Additional
(a) Test area
(1) Size (approximate average
proposed footing) ___________
(b) Test Apparatus
(1) Capacity ___________
(2) Sensitivity ___________
(3) Bracing ___________
(4) Settlement measuring
devices ___________
(5) Bearing plates
(c) Test procedure
(1) Load increments
___________
(2) Settlement ___________
(3) Duration ___________
(4) Rebound ___________
(d) Recording and analysis
(1) Time-settlement chart
___________
(2) Tabulated results
(interpretation) ___________
2. Site Preparation
(a) Salvage
(1) Buildings or parts
___________
(2) Trees and shrubs
___________
(3) Topsoil for storage
___________
(b) Clearing
(1) Old foundations: Break up
and Removal ___________
(c) Protection of
(1) Public: Barriers, Lights
and Other methods (when blasting, tree cutting, etc.) ___________
(2) Existing utilities and
structures ___________
(3) Pavements ___________
(4) Trees and shrubs: Boxing
or well ___________
3. Earthwork
(a) Permit
___________
(b) Layout
(1) Batter board: Set-back
___________
(c) Excavation
(1) Test borings or test pits
___________
(2) Cesspools or cisterns
___________
(3) Strata ___________
(4) Footing depths: Earth, Rock
and Not requiring forms ___________
(5) Undersoil for storage
___________
(d) Drainage
(1) Temporary ___________
(2) Permanent ___________
(e) Trenches
(1) Frost-line ___________
(2) Original bed ___________
(3) Protection (bracing)
___________
(f) Blasting safeguards for
(1) Life ___________
(2) Property ___________
(g) Existing structures,
foundations, utilities: Shoring
___________, Needling ___________ and Underpinning ___________
(h) Outside face of walls
(1) Clearances for inspection
___________
(i) Grades
(1) Specified ___________
(2) Extras, earth and rock: Estimates
___________, Authorization ___________ and Quantity ___________
(j) Fills
(1) Backfill ___________
(2) Grading ___________
(3) Tamping ___________
4. Utilities
(a) Excavations for service lines
___________
(b) Boxing or sleeves for pipelines
(1) Location ___________
(c) Drainage
(1) Lines, grades ___________
(2) Soil pipe ___________
(3) Tile installation
___________
5. Footings, Foundation Walls,
Piers
(a) Piling
(1) Wood: Species ___________,
Size ___________ and Treatment ___________
(2) Concrete:
Precast: Mix ___________, Tests ___________, Curing
___________ and Handling ___________
Cast-in-place: Shell design ___________ and condition
___________ | Mixes and slumps ___________
(3) Driving equipment: Type
___________ and Penetration per blow ___________
(4) Driving procedure:
Location and plumbness: Tolerances ___________, Protection
of underground utilities ___________, Excavation to cutoff levels ___________, Test
piles ___________, Uniformity and continuity ___________, Subsurface
obstructions ___________ and Redriving ___________
Use of follower: Mandrel for driving steel shells
Jetting ___________
(5) Records: Ground-water
levels Pile location ___________ and penetration ___________, driving
noncontinuity and Bearing capacities ___________
(6) Rejections: Damage
___________ and Nonconformance ___________
(7) Replacements: Redesign of
pile caps ___________, Rearrangement of pile groups ___________
Shells for cast-in-place' piles: Watertight condition
___________
(8) Withdrawn-piling spaces: Fill
___________
(9) Cutoflfs: Levels
___________, Splices ___________
Cast-in-place: Volume of concrete to fill shell
___________
Treated wood: Immediate coating after cutting off
___________
(b) Concrete
(1) Footings ___________
(2) Formed spaces:
Installation: Inserts ___________, Anchors ___________, Bulkheads
___________, Sleeves ___________, Steel for reinforcement ___________, Removal
of debris ___________ and Wetting of sandy bottom ___________
(c) Reinforcing
(1) Footings over pipelines
and utility trenches ___________
(2) Walls around temporary
openings ___________
(3) Lower-level walls and
piers: Splicing and Anchoring ___________
(d) Municipal approval
___________
6. Backfilling
(a) Prior to backfilling
(1) Subsurface masonry
___________
(2) Drain tile ___________
(b) Material for backfill
(1) Drainage characteristics
___________
(c) Track for heavy equipment
___________
(d) Trees
(1) Breathing space ___________
(2) Drainage ___________
(e) Topsoil protection
___________
No comments:
Post a Comment