Inspection Checklist for Concrete Placement | Pre, Post and during
Placement
To achieve greater strength and durability of the structural inspection
of concreting works is important. So we need to make all the checks during the inspection of concrete as a checklist. The checklist will be the record of concrete
placement and quality control measures taken on the site
We should have 3 types of checklists for concreting work
1. Checklist for Equipment and Material Preparation
2. Checklist for During Construction
3. Checklist for After concreting
We have explained all three types of checklists below,
STEP 1: CHECKLIST FOR CONCRETING WORK (Equipment and Material Preparation)
1. Aggregate for concrete material:
A. Excessive
dust is screened out from coarse aggregate.
B. Size
of aggregates is satisfactory as per specification.
C. Stone
chips must be made of crushed stone or boulder
D. Both
coarse and fine aggregates are free from all organic and deleterious materials.
E. Aggregates
are well stored on a brick flat solling platform.
F. Percent
wear of stone chips is below 30% tested by Los Angles Abrasion test.
G. Compressive
stone of stone aggregate shall not be less than 36.1 MPa or 5240 Psi.
H. Laboratory
tests confirm specifications mentioned in Sl. No. (8) and (9)
2. Grading of coarse aggregates:
A. 19mm
sieve size- passing 95-100% is confirmed.
B. 9mm
sieve size- passing 25-55% is confirmed.
C. No.
4 (4.76mm) sieve size- passing 0-10% is confirmed.
D. No.
8 (2.38mm) sieve size- passing 0-5% is confirmed.
E. Sieve
analysis is done and the report confirms the above criteria
3. Cement for concrete:
A. Types
of cement are CEM-1 as per specification.
B. Quality
of cement is satisfied as per specification.
C. Cements
are well stored, not in a moist environment.
D. Laboratory
test is done and the report confirms the above criteria
Other materials for concrete:
A. Admixture
as per specification is presented.
B. Water
is free from salt and other impurities.
C. Spare
Vibrator machines and vibrator nozzles are available.
D. Proper
levelling Instrument is available at the site.
E. Aggregate
measuring box and sand filter are present at the site.
F. Slump
testing apparatus is present at the site
G. Cylinder
testing equipment is present and in good condition.
STEP 2: CHECKLIST FOR
CONCRETING WORK (During Construction)
1. Mix proportion is checked by the
engineer:
a) Volume
of concrete is estimated and the target time is set.
b) Admixture
is used as per design specification
2. Manpower for concreting:
a) Site Engineer are present while mixing and placing concrete.
b) Work
assistant at the mixing point is deputed to count and control the batch as per
concrete pouring slip and load count slip.
c) Manpower
for mixing is enough with respect to the volume of work
d) During
casting sufficient shuttering men are kept for constant watch on the prop.
3. Adequacy of materials:
a) Mixing
portions of cement, aggregates and sand are investigated as per design
specification.
b) Adequate
Materials such as cement, aggregates and sand are presented with respect to the volume of work.
c) Aggregates
are properly soaked
d) Aggregates
are well graded.
4. Preparation at the site for concreting:
a) For
bonding with old concrete, the edges of old concrete are to be broken to give a
firm bonding.
b) Grouting
is used for construction joints. Electrical conduit is ensured in the proper place.
c) Rain
protection is arranged. Clear covers are monitored before placing concrete.
d) Casting
sequences are decided as per the consent of the engineer in charge.
5. Adequacy of equipment:
a) Chutes, and concrete buckets are cleaned and ready for use.
b) Adequate
Vibrator nozles are checked and ready for use.
c) Tower
crane for vertical lifting is provided.
d) Thickness
checking device is provided.
6. Mixing of Concrete:
a) Measured
quantity of materials as per proportion are dumped in the drum of mixture
machine.
b) Mixing
is executed with the required quantity of water for a period of not less than 2
minutes after all materials including the water are in the drum.
c) Proper
water-cement ratio is ensured by measuring slump as mentioned below:
a. Footing, pile cap, mass concrete 2" maximum
b. Precast pile, column, beam, slab 2.5" maximum
c. Ready mix concrete (with admixture) 4.0" maximum
7. After mixing concrete:
a) Workability
of concrete is adequate (slump is proper).
b) Cubes/
Cylinders are taken from the mixing for testing.
c) Slump
test is conducted and found OK.
8. Placing of concrete:
a) Water
is sprayed on the surface of the shutter/ steel shutter.
b) Concrete
is placed within 30 minutes after mixing the water.
c) Height
of free fall concrete is within 3 feet.
d) Concrete
is layed from one end, then continuously proceeded to the other end.
e) Fresh
concrete is deposited against concrete which is in position within 45 minutes.
f) Thickness
is checked at 3’-0’’ interval over the concrete slab.
g) Frequent
movement of labours/others over reinforcement is avoided during casting. Use of
plain sheet as a walkway for carrying concrete at the place.
h) During
casting, immediate remedial measures are taken in case props get loosened.
Compaction of Concrete:
a) For
beam and column, concrete compaction is done properly by the vibrator.
b) Compaction
is done within 15 minutes after the fresh concrete is placed in position.
c) Vibrating
is stopped as soon as the laitance of mortar appears on the surface. (Excessive
vibration segregates the mix.)
d) Vibrating
is executed properly in the vertical placement of the vibrator.
e) Vibrating
is executed without touching the re-bar.
f) Proper
surface vibration of slab surface with thick & plain wooden plank.
STEP 3: CHECKLIST FOR
CONCRETING WORK (After concreting)
a)
Movement
over a concrete surface is avoided within 24 hours.
b) Concrete surface is kept wet with water till
the removal of formwork.
c)
Keys in the
column-lift are provided for subsequent concreting in the proceeding days.
Click to download Inspection and Quality Work Checklist for Concrete Placement
Good information ♥️
ReplyDeleteTo fulfill your dream homes with the best technology and designs
ReplyDeletehome construction in bangalore