How to Calculate Cement and Sand Required for Floor Tiling? - LCETED - LCETED Institute for Civil Engineers

Post Top Ad

Sep 14, 2022

How to Calculate Cement and Sand Required for Floor Tiling?

How to Calculate Cement and Sand Required for Floor Tiling?

 

The calculation of the quantity of cement and sand required to install the floor tiles was done by using the following data

Also Read: How much Cement and Sand need for Tile flooring?

Cement and sand Mortar Mix Ratio

Mortar Layer Thickness

Floor Area for tile Installation

 

Let us Start, Calculation of Cement and sand for installing Floor Tiles on a 100Sqft Area

How to Calculate Cement and Sand Required for Floor Tiling?

 
 

Also Read: Tile calculator | tiles quantity estimator | skirting calculator

 

Tile Calculator | Tiles Quantity Estimator | Skirting Calculator


Consider Given Data:

Cement and sand Mortar Mix Ratio = 1:3 mix ratio

Mortar Layer Thickness = 1.5”

Floor Area for tile Installation = 100sqft

STEP 1: Calculation of Wet Volume of the Given area

 

Wet Volume = Area of Floor Tiling x Thickness of Mortar 

Wet Volume = 100 x 0.125 = 12.5scft

Wet Volume of Cement Mortar = 12.5scft


Dry Volume = 33% increase in Wet Volume

Dry Volume = Wet Volume + 33% Wet Volume

Dry Volume = 1.33 Wet Volume

Dry Volume of Cement Mortar = 1.33 x 12.5

Dry Volume of Cement Mortar = 16.625 cft



STEP 2: Calculation of Cement from Mortar Mix Ratio

 

Cement and sand Mortar Mix Ratio = 1:3 mix ratio

Sum of Mortar Mix Ratio Proportion = 1+3 = 4

 

Therefore,

 

Volume of Cement = (1/4) x 16.625 = 4.15625 cft

 

Provide 10% extra for Wastage

 

10% extra cement = 0.10 x 4.15625 = 0.415625 cft

 

Then, Total volume of cement = 4.15625 + 0.415625 = 4.57 cft

 

1 bag of cement = 1.226 Cubic Feet

Number of bags for 4.57 Cft = 4.57/1.226 = 3.72nos - 4 Nos

 

The number of bags required for 100 sqft installation of tiles will be 4 nos


 

 

Also Read: All you want to know about tiles

 

STEP 3: Calculation of Sand from Mortar Mix Ratio

 

Cement and sand Mortar Mix Ratio = 1:3 mix ratio

Sum of Mortar Mix Ratio Proportion = 1+3 = 4

 

Therefore,

 

Volume of Sand = (3/4) x 16.625 = 12.468cft

 

Provide 10% extra for Wastage

 

10% extra Sand= 0.10 x 12.468 = 1.2468cft

 

Then, Total volume of Sand = 12.468 + 1.2468 = 13.7148 cft

 

Volume of Sand Required for 100 sqft = 13.71 cft – 14cft

 

 


Also Read: How to calculate tiles quantity for a floor and wall? 

 

As a thumb rule, for Engineer, For 100 sqft Floor tile installation, we Required

4 Bag of Cement and 14 Cft of Sand

 

 

 

No comments:

Post a Comment

LCETED - "WHATSAPP GROUP"

For Instant updates Join our Whatsapp Group. Save our Whatsapp contact +919840140396 as LCETED and Send us a message “JOIN”

Post Bottom Ad