ACI Concrete Mix Design | American Concrete Institute (ACI) Method
Objective
To design a concrete mix by
ACI method for crushing strength of 150 mm cubes at 28 days is 20 MPa and slump
is 50 mm.
Theory and Scope
The absolute volume
procedure as recommended by the ACI mix proportioning method is used for
determining the proportions of the
ingredients for the concrete mixture. The method is suitable for normal and heavyweight concretes having a maximum
28-day cylinder compressive strength of 45 MPa and a workability (slump) range of 25 to 100 mm; the values generally
used in the applications are listed in Table below. The ACI method presumes that the workability of a mix with a given maximum size of well-graded aggregate (i.e., an aggregate with suitable particle shape and the grading)
is dependent upon the water content, the amount of entrained air and certain chemical admixtures, but is
largely independent of mix proportions, particularly the amount of cementing material. Therefore, ACI has
provided a table relating nominal maximum aggregate size, air entrainment and desired slump to the required
mixing water quantity.
In the ACI method, the bulk
volume of coarse aggregate per unit volume of concrete is estimated for
the maximum size of coarse aggregate and
fineness modulus of sand. The water-cement ratio is determined as in other methods to satisfy both strength and
durability requirements. The air content in concrete is taken into account in calculating the volume of fine
aggregate.
Apparatus
Sieve sets for finding maximum
nominal size and fineness modulus of coarse and fine aggregates respectively; Weighing balance; Trowels; Tamping bar;
Moulds, Universal compression testing machine; Graduated cylinder; Slump cone apparatus and Buckets.
Procedure
Step 1: Perform
the sieve analysis of both the fine and coarse aggregates to determine the maximum
nominal size of coarse aggregate and fineness
modulus of fine aggregate. Determine the unit weight, specific gravities, and absorption capacities of both
the aggregates.
Step 2: If
the workability in terms of a slump is not specified for a particular job; select
an appropriate value from the Table below
Slump ranges for specific applications (after ACI, 2000)
Types
of Construction |
Maximum
Slump, mm |
Minimum
Slump, mm |
Reinforced
foundation walls and footings |
75 |
25 |
Plain
footings, caissons, and substructure walls |
75 |
25 |
Beams
and reinforced walls |
100 |
25 |
Building
columns |
100 |
25 |
Pavements
and slabs |
75 |
25 |
Mass
concrete |
75 |
25 |
The maximum slump may be increased 25 mm for consolidation by
hand, i.e., rodding, etc.
Step 3: Estimate the mixing
water required for non-air-entrained concretes and entrapped air content from the Table
below
Approximate requirements of mixing water for
non-air-entrained concrete (after ACI 211.1 and ACI 318)
Slump, mm |
Mixing water quantity1,
kg/m3 |
|||||||
Specified nominal maximum size of aggregate (after CSA A23.1)
(mm) |
||||||||
10 |
14 |
20 |
28 |
40 |
562 |
802 |
1502 |
|
25 – 50 (Stiff-plastic) |
207 |
199 |
190 |
179 |
166 |
154 |
130 |
113 |
75 – 100 (Plastic) |
228 |
216 |
205 |
193 |
181 |
169 |
145 |
124 |
150 – 175 (Flowing) |
243 |
228 |
216 |
202 |
190 |
178 |
160 |
- |
Approximate amount of
entrapped air, per cent |
||||||||
All |
3.0 |
2.5 |
2.0 |
1.5 |
1.0 |
0.5 |
0.3 |
0.2 |
The table gives the maximum water content for reasonably well-shaped crushed aggregate.
The slump values are based on the slump made after the removal
of particles larger than 40 mm by wet screening.
Step 4: Determine the
target mean compressive strength of concrete at 28 days, ft by using the
ft
= fck + k (=1.65)S
where fck is the characteristic compressive
strength at 28 days, and S is the standard deviation.
Step 5: Determine the water-cement ratio from Table below
or Fig. below for the target mean strength computed in Step 4.
Relationship between water-cement ratio and
compressive strength of concrete
Compressive strength at 28 days, MPa |
Water-cement ratio by weight |
40 |
0.42 |
35 |
0.47 |
30 |
0.54 |
25 |
0.61 |
20 |
0.69 |
15 |
0.79 |
Maximum permissible water-cement ratios for concrete under severe exposure
Type
of Structure |
Continuously
wet structure exposed to frequent freezing
and thawing |
Structure
exposed to seawater or sulphates |
Thin
section (railings, curbs, sills, ledges, ornamental work) and sections with
less than 25 mm cover over steel |
0.45 |
0.40 |
All
other structures |
0.50 |
0.45 |
Step 6: Calculate
cement content from the water content and water-cement ratio determined in
Steps 3, 4 and 5, respectively, for the required strength and durability.
Step 7: Estimate
the coarse aggregate content from the Table below for the maximum nominal size of
the coarse aggregate and fineness modulus of sand.
Step 8: Determine
the content of fine aggregate by subtracting the sum of volumes of the coarse aggregate,
cement, water and entrained air from the unit volume of concrete.
Step 9: Fix
the concrete mix proportions for the first trial mix or trial mix no. 1. Make
suitable adjustments for moisture in the aggregates.
Relation between water-cement ratio and compressive strength of concrete
Bulk volume of coarse
aggregate per unit volume of concrete for different fineness moduli of fine aggregate
(Adapted from ACI 211.1)
Nominal
maximum size of aggregate (after CSA A23.1), mm |
Bulk volume of oven-dry-rodded coarse
aggregate, m3 Fineness modulus of fine aggregate
|
|||
2.40 |
2.60 |
2.80 |
3.00 |
|
10 |
0.50 |
0.48 |
0.46 |
0.44 |
14 |
0.59 |
0.57 |
0.55 |
0.53 |
20 |
0.66 |
0.64 |
0.62 |
0.60 |
28 |
0.71 |
0.69 |
0.67 |
0.65 |
40 |
0.75 |
0.73 |
0.71 |
0.69 |
56 |
0.78 |
0.76 |
0.74 |
0.72 |
80 |
0.82 |
0.80 |
0.78 |
0.76 |
150 |
0.87 |
0.85 |
0.83 |
0.81 |
Step 10: Measure
the workability of the trial mix in terms of slump using only as much water as
is needed to reach the desired slump (but
not exceeding the permissible w/c ratio). Carefully observe the mix for freedom from segregation and bleeding and
its finishing properties. Use the fresh concrete for unit weight, yield and air content.
Step 11: Recalculate
the mix proportions keeping the free water–cement ratio at the pre-selected
value; this will comprise trial mix no.
2. In addition, design two more trial mixes no. 3 and 4 with the water content same as trial mix no. 2 and varying
the free water–cement ratio by ±10 per cent of the preselected value.
Step 12: Cast
three 150 mm cubes for each trial mix and test them after 28 days of moist curing.
If required, a similar number of cubes may
be prepared and tested for early strength,.
Step 13: Analyse
mix nos. 2 to 4 for relevant information, including the relationship between
compressive strength and water–cement
ratio. Using this information compute the water-cement ratio required for the mean target strength. Recalculate the mix
proportions for the changed water–cement ratio taking water content as the same as that
determined in trial no. 2.
For field trials, produce the
concrete by the actual concrete production method used in the field.
Observations and Calculations
The compressive strength of concrete
is……. MPa.
This mix is suitable/it needs
revision.
The mix proportion is ……………..
Precautions
1. For calculating the
water-cement ratio, the surface moisture should be added to the water mixed
in concrete.
2. In choosing the strength
required for a particular purpose, allowance must be made for the inevitable variation in the strength of the test cubes. From
the specified minimum strength, the target means strength is estimated according to the degree of
control to be exercised, using information obtained from experience.
3. Slump test should be
completed within 30 minutes.
4. Contents should be
weighed accurately.
5. The inside of the cube
should be oiled to prevent the mortar from adhering to the sides of the mould.
6. The ambient temperature
at which cubes are prepared should be between 25 and 29°C.
Discussion
The method assumes that the
workability of a concrete mix is dependent only on the water content in the mix. The water content decreases with the
increase in the maximum nominal size of the coarse aggregate. The fraction of coarse aggregate itself decreases
with the increase of fineness modulus of fine aggregate, i.e., the coarser the sand lower will be the bulk volume
of dry coarse aggregate required for the mix. However, the coarse aggregate content increases with the increase
in the maximum nominal size of aggregate.
REFERENCES
ACI 211.1-91: Standard Practice for Selecting
Proportions for Normal, Heavyweight and Mass
Concrete, American Concrete Institute, Farmington Hills, Michigan, 1991.
ACI 211.4R-93: Guide for Selecting Proportions for
High-Strength Concrete with Portland Cement and Fly Ash, 1993.
ACI 211.5R-96: Guide for Submittal of Concrete
Proportions, American Concrete Institute, 1996.
ACI 211.3R-97: Guide for Selecting Proportions for
No-Slump Concrete, 1997.
ACI 211.2-98: Standard Practice for Selecting
Proportions for Structural Lightweight Concrete, 1998.
ACI 301-99: Specifications for Structural Concrete, 1999.
ASTM C39: Compressive Strength of Cylindrical Concrete
Specimens.
ASTM C617: Capping Cylindrical Concrete Specimens.
ASTM C192: Making and Curing Concrete Test Specimens in
the Laboratory.
The Better Co is a home construction company which helps you build your dream home and do your home interiors on one platform construction possible within your budget.
ReplyDeleteconstruction cost calculator