The first work to be taken before the actual construction of a building is checking the dimensions of its boundaries as soon as the site is made available for construction. The vital boundary stones should be in their position and they should be checked with reference to the survey plan. Any difference that may be found regarding the front, rear or side dimensions should be reconciled before the work is started
Also Read: Municipal
Requirements in Planning of Buildings | Building plan approval | Building
Permit
SITE LAYOUT
The site layout for construction consists of the layouts of
access roads, sheds, etc. They should be made as follows:
Access
roads. An examination of the site drawing will determine the best
layout for access roads. Wherever possible, access to the site for lorries and
carts should be the shortest and capable of carrying materials either to a
central place or various places of work, as may be desired.
Sheds. A
study of the site drawing will indicate where weatherproof sheds must be
erected for storage of materials such as cement, lime and other perishable
materials. If the cement stores have to be large, they should be provided with
two separate doors, one at each end one for accepting delivery and the other
for the issue of materials.
SITE CLEARING
Site clearing means any one or
all of the following works:
(i) Surface cleaning of grass,
trees, anthills, hillocks, etc.
(ii) Cleaning of obstructions that may be above or below
the ground level such as old foundations, old drainage works, old septic tanks,
pit-type latrines and soak pits
(iii) Cleaning of obstructions belonging to other
organizations such as drainage or water supply lines, underground electric or
telephone cables
In the case of the first two items, they should be suitably
removed and filled up to the ground level with good earth or sand. In the case of the
third item, the concerned party should be notified well before the commencement
of the work. If they are not to be disturbed during the construction, proper
arrangements should be made for their protection.
ENCLOSING THE SITE
The building site is enclosed
firstly for the safety of the public. If any person falls into an excavation made
for the building without an enclosure, the supervisor will be put to blame,
whereas if a person falls into an excavation in an enclosed area, that person
is a trespasser. Secondly, by enclosing the site, it becomes more secure from
any theft.
We should also ensure that the
methods of storing materials are safe. For example, if the material is stored
against a boundary wall, the wall should be strong enough not to fall down. If
gates are provided, they should be wide enough and properly located for the
lorry to come in. They should open inwards (not outwards) from the road.
WATER SUPPLY FOR CONSTRUCTION
Water is an important building
material. If groundwater is available, it should be tested suitably for various
uses. The cost of water comes to about one to two per cent of the cost of civil
works. If no groundwater is available and water connection can be obtained from
the municipal authorities, the pipes should be so laid that they will become
part of the permanent water supply system after the completion of the building.
If suitable water has to be
brought by lorries, temporary or permanent water storage tanks should be built
for storing a sufficient quantity of water for each day and also for discharge
from the supply tanker. If good groundwater is available, sinking a proper
tube well (which can also be used later) at a suitable place will ensure a good
supply of water during construction.
ELECTRICAL SUPPLY
Electricity
supply is necessary for modern building works. The points to be observed are as
follows:
1. Cables should be of good quality and suitably supported.
2. The switchboard, etc. must be properly enclosed and
capable of being locked.
3. The switchboard should be about 1.5 m above the ground
level.
PROTECTION OF EXISTING SERVICE LINES
Provision should be made to
protect water, electricity, telephone and other public distribution lines which
may be running through the property and be affected by foundation work.
We should mark all the
existing service lines so that workers can identify them and can be careful not
to disturb them during the construction. (There are many instances when
underground electric lines have been disturbed, causing fire to nearby
installations.) Sometimes, pipe ducts or concrete coverings are provided to
protect these services if they cannot be removed from the site to other
alternative places.
INITIAL CHECKS ON DRAWINGS
It is very important that before commencing actual setting
out of the building on the ground, the
following checks should be made on the drawing from which the layout is to be
carried out:
1. The sum of the intermediate dimensions should match with
those of the overall dimensions.
2. The levels of various constructions (such as ground
level with respect to road level, floor level, etc.) are clearly shown in the
drawing.
3. Check whether the proposed building will actually fit
into the plot with the mandatory distances specified by the municipal
authority.
SETTING OUT OF BUILDINGS
Setting out of buildings consists of the following two
operations:
1. The first operation is the setting out of centre lines.
This means establishing the centres of the walls in case of a building with
load-bearing walls, or the centre of columns in case of a framed building.
2. The second operation is the setting out of trenches or
establishing the excavation lines for proceeding with the excavation.
We will separately describe the procedures used for the
buildings with walls and for the framed buildings.
Must
read: Various
Steps In The Construction Of A Residential Building
Setting Out Centre Lines for Bearing Walls
The step-by-step procedure for setting out the centre lines
of walls can be stated as follows (as shown in Fig. below):
Step
1:
Establish a benchmark from which all levels for the various parts of the
building can be established and which will not be disturbed during the building
operations. This can be done by driving down a 50 mm x 50 mm angle 2 m long or
a steel rod of suitable diameter and 2 m length in a previously dug hole so as
to project about 10 cm from the ground level and then concreting the base to a
suitable depth below the ground level to form a pedestal around it.
Setting out centre lines and checking out
corners.
Step 2: The
second step is to mark a baseline from which all dimensions can be measured.
The centre line of the longest outer wall of the building is usually taken as
the baseline. This is marked with respect to the boundary.
Step
3:
The third step is to start from the baseline and mark the corner points of the
centre line of walls of a building by means of 50 mm x 50 mm wooden posts
driven firmly to the ground projecting 25 to 50 mm above the ground. A nail or
saw cut is placed on the peg to indicate the exact centre point. Setting
dimensions are measured with steel tapes and ranging roads between corner
posts. It is essential that the 90-degree angles at corners are calculated using a builder's square or the 3: 4: 5 principle or a theodolite.
Check whether all the dimensions of the diagonals tally.
Step 4: Using
the corner points, transfer the centre line to the ground with dry lime by
stretching lines between the pegs.
Setting Out of Trenches for Excavation of Bearing Walls
Having set up the centre line of corners and checked the
dimensions of the building on the ground, we proceed to set out the lines for
trenches using the centre line already established.
The aim of setting out trenches is to mark the direction
and width of excavations to be carried out and also to mark the width of the
wall to be built. This is carried out by using pegs or by profile boards.
These are masonry pillars or timber boards fixed to the
ground some distance away from the exaction on which the excavation and wall
boundaries can be marked as shown in Fig. below. These are set up at least 2 m
clear of the excavation as shown in Fig. below. The profile boards may be
masonry or timber.
The level of the top of the profile boards should be
related to the side datum level and fixed at a convenient height if a boning rod
(a traveller) is used to control the depth. The centre line, wall width and
trench width are marked on the profile board. The trench width is marked on the
ground by lime powder after stretching strings between the profile boards.
Setting out of trenches.
Setting Out a Framed Building
For setting out the foundation of a framed building also,
we first establish the benchmark and set out the centre line of columns. This
is usually carried out by a theodolite as the column centre lines are usually
marked on a grid as shown in Fig. 2.3—one axis is marked as 1, 2, 3, 4, etc.
and the other as A, B, C, D, etc.
Setting out footings of framed buildings by theodolite (I
to Ill positions of theodolite).
In this case, we first fix all
the peripheral points as shown in Fig. above. We first fix point 4 with respect
to the boundaries of the plot. Then we station a theodolite at point 4 and fix
F4, E4 to B4. Turn 90° and fix A3 to A 1. Secondly, fix theodolite at A 1 and
fix B1 to Fl. Thirdly, station theodolite at F and fix F2 to F4 (check F4). The
internal points can then be fixed easily by a theodolite or with stretched lines.
Once the grid has been set out, profile boards can be fixed clear of excavation
work to carry the excavation of the footings.
METHODS TO DETERMINE DEPTH OF EXCAVATION
For the construction of
foundations and sewer drains, the depth of the base of the excavation is
usually set out by means of sight rails and boning rods (also called traveller)
as shown in Fig. below. In foundation, construction the base is to be
levelled and for drain construction, it is to be laid to the required gradient.
This operation is fully dealt with in surveying.
Another method that can be
used for levelling of the foundation is the use of a water level. A plastic tube is
filled with water and is used as a water level. First, the required depth of
excavation is excavated in one place. In all the other sites, the level is
determined by means of the water level with reference to this point. One more
method is the use of the traditional levelling staff.
Determination of depth of excavation by
boning rod or traveller and profile boards: 1. Strip foundation, 2. Column
footing.
CONCLUSION: The procedure of site preparation and setting out of works is an important item of work as the final dimensions of the building and the sizes of various rooms depend on this operation. It should be carried out with precision by an experienced person.
Must
read: How
To Control Cost In Home Construction
FAQ
What is the 3 4 5 triangle method in setting up a building?
To get a complete square corner, we need to aim for a
measurement ratio of 3: 4: 5. In other words, our straight line should be three
feet long, and our vertical four feet long should be perpendicular, and our
cross five feet long. If all three measurements are correct, we will get a
complete square corner. We can also use multiples of 3:4:5 like 6:8:10 or
9:12:15
What is meant by setting out of buildings?
Setting out of buildings consists of the following two
operations:
The first operation is the
setting out of centre lines. This means establishing the centres of the walls
in case of a building with load-bearing walls, or the centre of columns in case
of a framed building.The second operation is the setting out of trenches or
establishing the excavation lines for proceeding with the excavation.
What is setting out a plan drawing?
"Setting out" is the process of finding points
for columns, site boundary level, pile level and other required structural
areas according to the construction diagram.
No comments:
Post a Comment