The following points are the sequence of operations for
the safe installation of PVC / GI pipes and components in bricks/block
masonry according to standard procedure and code.
1. Make sure the bricks/block masonry work is completed
and prepared for electrical work.
2. Check if the FFL (Finished Ground Levels) reference is marked.
Electrical Chases in
Brick Wall Sequence of Operations With Guidance
Marking of Switch Box and Light Points
1. Switch, sockets, light and foot lamp location and conduit
route marked on the wall with proper height based on approved shop drawing.
2. Do not use any conduit smaller than 20 mm in diameter
or larger than 32 mm in diameter.
3. Specify the location of the switch box, DP, and
junction box from the FFL to the light point on the wall.
Wall Chasing:
1. After marking the route and switch box location, wall
chasing should be done using a wall cutting machine.
2. Using Hammer and chisel the chased portion chipped in
the depth of 2” to 3” mm or as per standard specifications.
3. Wall chases should be
inspected for accommodation space for outlet boxes, switch/point control boxes,
data boxes to be fixed along with conduits.
4. Power conduits should not be run near any data line
5. Elbows and bends should not be used. If there is a
change in the direction of the pipe, use a spring to bend the pipe.
Note: Chasing
work shall be carried out after completion of curing of brickwork (at least 7
days gap from brickwork)
Installation of conduit pipes
1. If the length of the pipe flow is more than 10 m, a junction
box shall be provided for periodic inspection and replacement of wires if
necessary. These should be flush wall mounted.
2. Conduit pipe is placed in the chases using concrete
nails. Nail shall be maintained at 2 feet at intervals.
3. Conduit pipes should be concealed with chicken mesh
before plastering
Installation of Switch Board / Distribution box
Note:
DB
Wall blockwork/brickwork thickness should be 9” minimum
1. DB and switch box should be installed in locating the plaster
level points (button mark given for plastering). (note: 3 mm below the
plastered surface)
2. The mounted height of
the Switch Board is generally
) The height of the switchboard
must be 1.3m to 1.75m from floor level
) The height of the distribution
board must be 1.5m to 1.75m from floor level
) The bottom of the
ceiling fan should have a minimum clearance of 2.75m
) All lamps should be
fitted with a minimum clearance of 2.75m above floor level
) 300 mm near the bed
General
according to the approved drawings.
3. Confirm the size of the
box and cut the box slightly larger with sufficient depth at the marked
location of the block/brick wall accordingly.
4. Adjust the GI metal box to the appropriate size and
level with the help of the Spirit level.
5. The switch box and DP were installed using cement
mortar around the box. Make sure it is fixed flush with plaster level.
6. The switch box/junction box bottom level should mark
level as per consultant approved height as per local applicable wiring
regulation requirements.
7. The spacing between the two switchboards should be
the same for all installations (note: minimum 3” space between box).
8. Junction box and switch box should be covered and
secured with brown tape filled with paper and a gunny bag.
How is Wall Chasing Done?
During floor or wall treatment, hand-held cutting tools provided with cutter
machine are used to cut conduit pipe route locations of specific depth and width in
brickwork. Then using a small breaker or hammer drill the centre part of the
concrete blocks/bricks is removed. This technique is quick and dust-free.
How to Fill Electrical wall Chase?
Once the conduit is installed. Using mesh sealed the
conduit to avoid cracks. Then close the chase using filler
As a filler is cement mix
Cement
mix
- 3:1 – 3 parts of soft sand: 1 part of cement.
MUST READ: HOW DO YOU INSTALL ELECTRICAL CONDUIT ON CONCRETE SLAB?
If you find
This information is helpful, please share it.
Thanks! For reading the article...
As per national building code india horizontal cutting of walls are not allowed more than one meter !!!! Then how can do conduit in wall ?
ReplyDelete9446454198
ReplyDelete