Setting Out Works
In This Article,
We Explained About How To Setting Out A Building, Culvert And Location Of
Bridge Pier With A Simple Procedure And Diagram
SETTING OUT A BUILDING
A building is set out in order to clearly define the
outline of excavation and the centre lines of the walls so that construction
can be carried out exactly according to plan. The centre-line method of setting
out is generally preferred and adopted.
Procedure
1. From the plan, the centre lines of the walls are
calculated. Then the centre lines of the rooms are set out by setting
perpendiculars in the ratio 3: 4: 5. Suppose the corner points are A, B, C, D,
E, F, and G which are marked by pegs with nails on top.
Fig. 1 Centre-line Method
2. The setting of the corner points is checked according
to diagonals AC, BD, CF and EG.
3. During excavation, the centre points A, B, C,… may be
removed. Therefore, the centre lines are extended and the centre points are marked
about 2 m away from the outer edge of the excavation. Thus, the points A1, A2, B1,
B2,… are marked outside the trench. The centre lines are shown clearly by
stretching thread or rope. The centre points fixed 2 in away from the
excavation are marked with stout pegs.
4. From the plan, the width of excavation is found out
and set out around the centre line. The excavation width is also marked by
thread with pegs at appropriate positions.
5. The excavation width is then marked by lime or by
making a furrow with a spade.
6. If the plan is much too complicated and follows a
zig-zag pattern, the centre pegs are kept at suitable positions according to
site conditions.
SETTING OUT A CULVERT
The abutments and wing walls of a culvert are set out by
coordinates from the centre of the culvert, which is taken as the origin.
From the plan, the coordinates of different points on
the abutments and wing walls are calculated as tabulated as follows:
Point |
Coordinate |
Remark |
|
x |
y |
||
P1 |
x1 |
y1 |
Data calculated for left half of culvert |
P2 |
x2 |
y2 |
|
P3 |
x3 |
y3 |
|
P4 |
x4 |
y4 |
As the culvert is symmetrical about both the axes, the
necessary data for the right half are similar to those for the left half.
Again, the data for both sides of the X1X line are similar (
Fig. 2 ).
Procedure
Fig. 2 Setting Out a Culvert
1. The axes (centre line) X X1 and Y Y1
are set out, with O is the origin.
2. Along the line OX1, points 1, 2, 3 and 4
are marked at distances x1, x2, x3 and x4 from origin.
3. Now Along OY, points 1′, 2′, 3′ and 4′ are marked at
distances y1, y2, y3, and y4 from
O.
4. Now two tapes are taken with their zero ends together
and held at P1 by the overseer in such a way that when two
assistants hold them fully stretched at 1 and 1′, the readings are exactly equal
to y1 and x1 (i.e. P11 = y1 and P11′
= x1). Then the point P1 is marked with a stout peg.
5. Similarly, the other pegs are fixed at P2,
P3 and P4. The pegs for the right half are fixed
according to the data available from the table prepared for the left half. The
culvert is symmetrical about the centre line X X1. So, the other
half can be easily set up.
LOCATION OF BRIDGE PIER
The procedure for locating a bridge pier is as follows:
Procedure
1. The centre line AB of the bridge is ranged by setting
a theodolite at A and two stout pegs are fixed at T1 T2
on the line AB ( Fig. 3 ).
Fig. 3 Locating a Bridge Pier
2. The effective length of the bridge (S1S2)
is determined by triangulation or by the stadia method.
3. The number of spans and the width of each are
theoretically ascertained and plotted in a plan.
4. A baseline AC is taken perpendicular to the centre
line AB. The distance AC is accurately measured by invar tape.
5. On the plan points S1 and S2
represent the centres of abutments and points P1 and P2
the centres of piers.
6. The distance AS1 is measured accurately by
invar tape.
7. From the effective width of the bridge, the widths of
spans S1P1, P1 P2 and P2
S2 are ascertained.
8. Then the angles θ1, θ2, θ3
and θ4 are calculated as follows.
and so on.
9. Another theodolite is set up at C and the angles θ1,
θ2, … are set out in the usual manner.
10. The line of sight of the theodolite at A and that of
the theodolite at C will intersect at points S1, P1, P2,
and S2. These points are marked in position accurately.
11. In order to ensure extreme accuracy, the centre
lines of the piers are checked by setting a theodolite on a baseline taken on
the other bank of the river.
If you find
This information is helpful, please share it.
Thanks! For reading the article...
Good reference
ReplyDelete"Consistently delivering top-tier cleaning services daily." Building Maintenance
ReplyDelete