LIFT-PIT CALCULATION | QUANTITY SURVEY | VOLUME OF CONCRETE & AREA OF SHUTTERING
For a given drawing of Lift-Pit find
1. Volume of Concrete
2. Area of Shuttering
1. Plain Cement Concrete Bed:
L = 2.30m ; B = 2.0m ; T = 0.10m
(a)
Volume Of Concrete For P.C.C Bed = Area X Thickness Of P.C.C Bed
= L
x B x D
= 2.30 x 2.0 x 0.10
=
0.46 m3
(b)
Shuttering Area For P.C.C Bed = (L+B) x 2 x D
= (2.30 + 2.0) x 2 x 0.10
=
0.86 m2
2. Bottom slab:
L = 2.10m ; B = 1.80m ; T = 0.20m
(a)
Volume of Concrete for Bottom slab = area x thickness of bottom slab
= L
x B x D
= 2.10 x 1.80 x 0.20
=
0.756 m3
(b)
Shuttering area for Bottom slab = (L+B) x 2 x D
= (2.10 + 1.80) x 2 x 0.20
=
1.56 m2
3. Shear Wall Along Horizontal Plane :
L = 2.10m ; B = 0.20m ; H = 1.20 m
(a)
Volume of Concrete for Shear wall = area x depth x no. of walls
= L
x B x D x no.s
= 2.10 x 0.20 x 1.20 x 2
=
1.008 m3
(b)
Shuttering area for Shear wall = L x D x 2 x no.s
= 2.10 x 1.20 x 2 x 2
=
10.08 m2
4. Shear Wall Along Vertical Plane:
L = 1.40m ; B = 0.20m ; H = 1.20 m
(a)
Volume of Concrete for Shear wal= area x depth x no. of walls
= L
x B x D x no.s
= 1.40 x 0.20 x 1.20 x 2
=
0.672 m3
(b)
Shuttering area for Shear wall = L x D x
2 x no.s
= 1.40 x 1.20 x 2 x 2
=
6.72m2
5. Plat‐forms:
L = 0.40m ; B = 0.40m ; H = 0.50 m
(a)
Volume of Concrete for Plat‐form = area x depth x no. of plat‐forms
= L
x B x D x no.s
= 0.40 x 0.40 x 0.50 x 2
=
0.16 m3
(b)
Shuttering area for Plat‐form = (L + B) x
2 x D x no.s
= (0.40 + 0.40) x 2 0.50 x 2
=
1.60 m2
(i) Total Volume of Concrete for Lift‐Pit = 0.46 + 0.756 + 1.008
+ 0.672 + 0.16 = 3.056 m3
(ii) Total Shuttering area for Lift‐Pit = 0.86 + 1.56 + 10.08
+ 6.72 + 1.60 = 20.82 m2
Must read: Hardy Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Waffle Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Pitch Roof Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Semi‐Round Stair‐Case Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Ramp Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must
read: Dome
Slab Calculation | Quantity Survey | Volume Of Concrete | Area Of Shuttering
If you find
This information is helpful, please share it.
Thanks! For reading the article...