1. Dome Slab Volume Of Concrete Calculation
2. Dome Slab Area Of Shuttering Calculation
GIVEN DATA
(A) Solution for Roof Slab
1. Volume of Concrete = Area x Depth x no.
of Slabs
= L x B x D x no.s
= 14.50 x 10.50 x 0.20 x 1
=
30.45 m3
Deduction of Dome area
(i)
Dome‐1 = Area x Depth
= π/4 x d2 x D
= π/4 x 2.502 x 0.20
= π/4 x 6.25 x 0.20
= 0.981
m3
(ii)
Dome‐2 = Area x Depth
= π/4 x d2 x D
= π/4 x 1.852 x 0.20
= π/4 x 3.4225 x 0.20
= 0.537
m3
(iii)
Dome‐3 = Area x Depth
= π/4 x d2 x D
= π/4 x 1.652 x 0.20
= π/4 x 2.7225 x 0.20
=
0.427 m3
Total volume of concrete required = 30.45 ‐ 0.981‐ 0.537 ‐
0.427
= 24.859 m3
2. Shuttering area = (Bottom area of floor
slab + peripheral length of Dome‐1 x Depth + peripheral length of Dome‐2 x
Depth + peripheral length of Dome‐3 x Depth)
= L x B + 2 x π x r1
x D + 2 x π x r2 x D + 2 x π x r3 x D
r1 = 1.25
r2 = 0.925
r2 = 0.825
= 14.50 x 10.50 + 2 x π x 1.25 x 0.20 + 2 x π x 0.925 x
0.20 + 2 x π x 0.825 x 0.20
= 156.01 m2
Deduction of Dome area
(i) Dome‐1 = Bottom Area of Dome‐1
= π/4 x d2
= π/4 x 2.502
= π/4 x 6.25
= 4.90 m2
(ii) Dome‐2 =
Bottom Area of Dome‐2
= π/4 x d2
= π/4 x 1.852
= π/4 x 3.4225
= 2.68 m2
(iii) Dome‐3 = Bottom Area of Dome‐3
= π/4 x d2
= π/4 x 1.602
= π/4 x 2.7225
= 2.13 m2
Total
shuttering area required = 156.01 ‐ 4.90 ‐ 2.68 ‐ 2.13
= 146.3 m2
(B) Solution for Dome Slabs
DOME-1:
Semi‐Circle Length = 2 Ï€ R x ½
= 2 x π x 1.25 x 0.5
= 3.92 m
1. Volume of Concrete = Area x Depth
= π/4 x d2 x D
= π/4 x 3.922 x 0.15
= π/4 x 15.36 x 0.15
= 1.80 m3
2. Shuttering area = bottom area of dome
= π/4 x d2
= π/4 x 3.92 2
= π/4 x 15.36
= 12.06 m2
DOME-2:
Semi‐circle length = 2 Ï€ r x ½
= 2 x π x 0.925 x 0.5
= 2.90 m
1. Volume of Concrete = Area x Depth
= π /4 x d2 x D
= π /4 x 2.902 x 0.15
= π /4 x 8.41 x 0.15
= 0.99 m3
2. Shuttering area = bottom area of dome
= π/4 x d2
= π/4 x 2.902
= π/4 x 8.41
= 6.60 m2
DOME-3:
Segmental arc length = (8B‐2R)/3
Where,
B =
√R2 + H2
Therefore,
D= 1.65m; R = 0.825m; H = 0.60m
B =
√R2 + H2
B =√0.8252 + 0.602
B = 1.02
Arc length 'L' = (8 x 1.02 ‐ 2 x 0.825)/3
= 2.17m
1. Volume of Concrete = Area x Depth
= π /4 x d2 x D
= π /4 x 2.172 x 0.15
= π /4 x 4.70 x 0.15
= 0.55 m3
2. Shuttering area = bottom area of dome
= π /4 x d2
= π /4 x 2.172
= π /4 x 4.70
= 3.69 m2
(C) Solution for Minaret
Cylinder:
1. Volume of Concrete = Area x Depth
= π/4 x d2 x D
= π/4 x 0.602 x 3.50
= π/4 x 0.360 x 3.50
= 0.989 m3
2. Shuttering Area = Peripheral length x depth
= 2 x π x r x D
= 2 x π x 0.30 x 3.5
= 6.597 m2
Cone:
1. Volume of Concrete = Area x Depth x 1/3
= π/4
x d2 x D x 1/3
= π/4 x 0.802 x 1.20 x 1/3
= π/4 x 0.64 x 1.20 x 1/3
= 0.20 m3
2. Shuttering Area = Peripheral length x depth x 1/3
= 2
x π x r x D x 1/3
= 2 x π x 0.40 x 1.20 x 1/3
= 1.00 m2
CALCULATION FOR THE QUANTITIES OF ROOF SLAB WITH DOME
SLAB
S.no |
Description |
item |
no.s |
length in metre |
Breadth in metre |
Depth in metre |
Volume of Concret in m3 |
area of shutter in m2 |
Remarks |
1 |
Floor Slab |
S |
1 |
14.500 |
10.50 |
0.200 |
24.859 |
156.01 |
|
|
|
|
|
|
|
|
|
|
|
|
Deduction
of area |
|
|
|
|
|
|
|
|
|
Dome‐1 |
DM1 |
1 |
Ǿ = |
2.5 |
0.200 |
‐0.981 |
‐4.90 |
|
|
Dome‐2 |
DM2 |
1 |
Ǿ = |
1.85 |
0.200 |
‐0.537 |
‐2.68 |
|
|
Dome‐3 |
DM3 |
1 |
Ǿ = |
1.65 |
0.200 |
‐0.427 |
‐2.13 |
|
|
|
|
|
|
|
|
|
|
|
2 |
Dome |
|
|
|
|
|
|
|
|
|
Dome‐1 |
DM1 |
1 |
Ǿ = |
3.92 |
0.150 |
1.80 |
12.06 |
|
|
Dome‐2 |
DM2 |
1 |
Ǿ = |
2.90 |
0.150 |
0.99 |
6.60 |
|
|
Dome‐3 |
DM3 |
1 |
Ǿ = |
2.17 |
0.150 |
0.55 |
3.69 |
|
|
|
|
|
|
|
|
|
|
|
3 |
Minaret |
|
|
|
|
|
|
|
|
|
Cylinder |
cyl |
1 |
Ǿ = |
0.600 |
3.500 |
0.989 |
6.597 |
|
|
Cone |
cone |
1 |
Ǿ = |
0.800 |
1.200 |
0.20 |
1.00 |
|
|
|
|
|
|
|
TOTAL |
29.255 |
159.602 |
|
Must read: Hardy Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Waffle Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Pitch Roof Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Semi‐Round Stair‐Case Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
Must read: Lift-Pit Calculation | Quantity Survey | Volume Of Concrete And Area Of Shuttering
Must read: Ramp Calculation | Quantity Survey | Volume Of Concrete & Area Of Shuttering
CALCULATION FOR THE QUANTITIES OF ROOF SLAB WITH DOME SLAB EXCEL SHEET
If you find
This information is helpful, please share it.
Thanks! For reading the article...
Am so proud of civil knowledge, with you we can make the world a better place for living Warm wishes and best regard
ReplyDelete