RAMP CALCULATION | QUANTITY SURVEY | VOLUME OF CONCRETE & AREA OF SHUTTERING
For a given drawing of Lift-Pit find
1. Volume of Concrete
2. Area of Shuttering
(A) Solution for Ramp:
1. Ramp at the entrance:
L =
10.547 m ; B = 4.0m ; T = 0.20m
c = Ñ´(a2 + b2)
c = Ñ´(9.802 + 3.902)
c =
10.547m
(a)
Volume of Concrete for Ramp = area x
thickness of Ramp
= L x B x D
= 10.547 x 4.0 x 0.20
=
8.437 m3
(b)
Shuttering area for P.C.C bed = (L+B) x 2 x D
= (10.547 + 4.0) x 2 x 0.20
=
5.81 m2
2. Ramp at exit:
L = 10.547 m ; B = 4.20m ; T = 0.20m
c = Ñ´(a2 + b2)
c = Ñ´(9.802 + 3.902)
c =
10.547m
(a)
Volume of Concrete for Ramp = area x
thickness of Ramp
= L x B x D
= 10.547 x 4.20 x 0.20
=
8.859 m3
(b)
Shuttering area for P.C.C bed
= (L+B) x 2 x D
= (10.547 + 4.20) x 2 x 0.20
=
5.89 m2
(i) Total Concrete for both Ramps =
8.437+ 8.859 = 17.296 m3
(ii) Total Shuttering area for both Ramps = 5.81 + 5.89 = 11.70 m3
Must
read: Hardy
Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of
Shuttering
Must
read: Waffle
Slab Calculation | Quantity Survey | Volume Of Concrete & Area Of
Shuttering
Must
read: Pitch
Roof Calculation | Quantity Survey | Volume Of Concrete & Area Of
Shuttering
Must
read: Semi‐Round
Stair‐Case Calculation | Quantity Survey | Volume Of Concrete & Area Of
Shuttering
Must
read: Lift-Pit
Calculation | Quantity Survey | Volume Of Concrete And Area Of Shuttering
Must
read: Dome
Slab Calculation | Quantity Survey | Volume Of Concrete | Area Of Shuttering
If you find
This information is helpful, please share it.
Thanks! For reading the article...
No comments:
Post a Comment