Combined Isolated footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint - LCETED - LCETED Institute for Civil Engineers

Post Top Ad

Nov 6, 2021

Combined Isolated footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Combined Isolated‐footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

 

1. Combined Isolated‐footing Volume Of Concrete Calculation

2. Combined Isolated‐footing Area Of Shuttering Calculation

3. Combined Isolated‐footing Area Of Bitumen Paint Calculation


Combined Isolated‐footing Quantity Survey


 

Footing dimension:

Bottom dimension: L1 = 0.85m; B1= 0.85m

Top dimension: L2 = 0.50m; B2 = 0.50

Depth of Footing = 0.91m

C 1= 0.35 x 0.35

C 2= 0.40 x 0.40

 

Solution:

1. Volume of Concrete = Area x Depth

Part‐1: = L x B x D

= 2.40 x 1.0 x 0.45

= 1.08 m3

Therefore Average length "L" = (L1 + L2)/2

= (2.80 + 2.0)/2

= 2.40m

 

Therefore Average Breadth "B" = (B1 + B2)/2

= (1.20 +0.80)/2

= 1.0m

 

Volume of Concrete = Area x Depth

Part‐2: = L x B x D

= 2.80 x 1.20 x 0.25

= 0.84 m3

 

Total Volume Of Concrete For The Footing = Vol. Of Part‐1 + Vol. Of Part‐2

= 1.08 + 0.84

= 1.92m3

 

2. Shuttering Area = Peripheral Length x Depth

Part‐1:

= (L + B) x 2 x D

= (2.40 + 1.0) x 2 x 0.45

= 3.06 m2

 

Part‐2:

= (L + B ) x 2 x D

= (2.80 + 1.20 ) x 2 x 0.25

= 2.0 m2

 

Total Shuttering Area For The Footing = Area. Of Part‐1 + Area Of Part‐2

= 3.06 + 2.0

= 5.06 m2

 

3. Bitumen Paint Area = Peripheral Length X Depth + Top Area ‐ Column Area  Part‐1:

= (L + B ) x 2 x D + L x B ‐ L x B (Column area)

= (2.40 + 1.0 ) x 2 x 0.45 + 2.0 x 0.80 ‐ (0.35 x 0.35 + 0.40 x 0.40 )

= 4.3775 m2

 

Bitumen Paint Area = Peripheral Length X Depth Part‐2:

= (L + B ) x 2 x D

= (2.80 + 1.20) x 2 x 0.25

= 2.0 m2

 

Total Bitumen Paint Area For The Footing = Area. Of Part‐1 + Area Of Part‐2

= 4.3775 + 2.0

= 6.3775 m2


Must read: Plain Footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Must read: Plain Combined Footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Must read: Shoe footing Quantity Survey | Eccentric Footing | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Must read: Raft footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Must read: Step footing Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint

Must read: Pile under footing (pile‐cap) Quantity Survey | Volume Of Concrete | Area Of Shuttering | Area Of Bitumen Paint


If you find 


This information is helpful, please share it.

 

Thanks! For reading the article.......


No comments:

Post a Comment

LCETED - "WHATSAPP GROUP"

For Instant updates Join our Whatsapp Group. Save our Whatsapp contact +919840140396 as LCETED and Send us a message “JOIN”

Post Bottom Ad