A huge amount of money is invested in the construction of
buildings bridges and roads. Economical consideration needs the earliest use of the
investment and hence present-day demand is automation in construction. To meet this challenge lot
of research has gone into and a number of techniques are developed. In this
chapter, the automation in buildings, dams, bridges and road constructions are
briefly discussed.
AUTOMATION IN BUILDING CONSTRUCTION
Digging for
Foundation
Any construction work starts with digging for the foundation. Nowadays manual digging for foundations is almost given up in all
cities and towns. JCB is used for this purpose which can finish digging work
for most of the buildings in a day or two.
Mining, Lifting, Transporting and Placing of Concrete
Labour oriented method of mixing, lifting, transporting
and placing of concrete needs to be changed to the mechanisation of concreting.
Without it speed and economy cannot be achieved in construction.
Batching and mixing plants
In large projects like dam construction or in ready-mixed
concrete plants large batching and mixing plants are used. Ready-mixed
concreting is a new concept in which concrete mixing is done in large plants and
then transported to needy places in the city. The capacity of such plants
varies from 120-150 cubic metres per hour. These concrete production plants
comprise of:
1. Silos, containers and bins for storage of raw
materials.
2. Batching arrangement.
3. Measuring and recording equipment.
4. Mixing equipment.
5. Control system.
6. Electrical, hydraulic and pneumatic drives.
7. Conveying systems like belt/screw conveyors.
Cement is generally stored in silos. The silos are
loaded with cement with the help of pneumatic blowers. If bagged cement is used
then tree cement is loaded using a compressed air loader and a splitter unit.
Water is generally stored in tanks located close to the
plant.
Aggregates are stored in silos. A storage capacity of
1500 m3 is possible.
Cement silos are provided with weigh hoppers that use the knife-edge balance principle. Larger plants use the electromechanical system. For
measuring water a water meter or a water batch is used. The aggregates weighers
are generally identical to the cement weighers in the plant.
The aggregates and cement are first to dry mixed in hoppers
using scrappers.
Provision is made up to four types of concrete admixtures
to be added with the required quantity. Freefall or power mixers are used for
thorough mixing of concrete.
Fully automatic plant control systems with multiple
inputs are based in a container or control room.
The figure below shows a typical batching plant
Concrete batching plant
Fig.
below shows a microprocessor control system in a mining plant.
Microprocessor control system in
concrete batching mixing plant
Transportation and Placing
Various modes of
transporting concrete are truck agitators, truck miners, cranes, buckets,
elevators, belt conveyors, concrete pumps, chutes etc. The suitability of method
of mechanical transportation varies from job site to job site. Often a combination of various methods is also used. It may be noted that truck
agitators, truck miners are useful for horizontal transport, while cranes,
buckets, elevators, belt conveyors and pumps are useful for vertical transport.
Chutes are useful for dropping concrete in intricate portions.
Mini batching plants are
suitable for projects like national highways, flyover, mass housing and
industrial projects. They have a capacity of 15 to 20 m3 per hour. The plant
includes:
1. Inbuilt weighing system for fine and coarse
aggregates.
2. Automated loading system for aggregates.
3. Cement hopper with weighing system.
4. Automatic admixture dozing system.
5. Print out the system giving details of batching and
mixing. The figure below shows a mini batching plant.
Mini batching plant
Self Compacting Concrete (SCC)
Self-compacting concrete (SCC) as the name signifies
should be able to compact itself without any additional vibrations or
compaction. It was first developed in the late 1980s. It is highly flowable within
the formwork and fills it without any external vibration. This is used to
ensure the filling of congested sections. It includes a high amount of superplasticizers and cement to increase flowability. Viscosity agents are also
added. The mix may incorporate steel or polypropylene fibres also. The sand can
be finer.
In Sweden, bridges are built with SCC. In Japan, two
anchor blocks were constructed in the Akashi-Kailro bridge. In France, SCC is
preferred in cities as noise-free concreting. Since there are no vibrations in
compacting, formworks can be reused several times. The use of SCC is becoming
popular in precast industries also.
Prefabricated Structural Elements
The use of prefabricated structural elements increases the construction speed and quality of the structural elements. It saves time because the casting of these elements can start much early in factories much before they
are to be put in the building. For building activity, the requirement of time is
only for putting them in the structure. Some of the commonly used prefabricated
structural elements are :
1. Precast
concrete portions: Precast concrete posts and panels of sizes
1000 × 400 × 40 mm are as shown in Fig below.
Precast concrete posts and panels
Prefabricated roof truss and reapers
for Mangalore tiled roof
2. Precast
roofing units: In Pune, the universal temple of Ramakrishna
was built with suitable elements to form the required geometric forms of Shikharas.
The technique of using precast elements has saved construction time by at least
6 to 8 months. After erecting shell units the outer surface of roofs and domes
are covered with Glass Mosaic Tiles laid in polymer modified tile adhesive,
giving excellent aesthetic view and weatherproofing.
3. Lift
slab construction: In this construction, slabs are cast at
ground level one over the other with separators in between. Then slabs are
lifted along columns to their positions using cranes or jacks and clamped. This
process has been applied to a two-storeyed building built at Roorkee by Central
Building Research Institute. It is possible to extend the technique to multi storeyed structures with several floors. In America, this has been tried
successfully.
Form Works
Providing form works takes considerable time in
building construction. The conventional method of providing wooden formwork needs
modernisation. Steel form works consisting of steel plates, rods and pipes are
gradually replacing conventional wooden formwork. Steel formwork is speedy;
give a good finished surface and is safe too.
In the construction of silos and chimneys slip forms are
used. The formwork is clamped to an already built portion of the structure with
about 1 to 1.5 m protection. As the upper portion is built, formwork is slid
up and fixed to the newly cast portion. It saves the cost of formwork and speeds up
the construction activity.
Application of Robots for Building Automation
It is desirable to have robots for building automation
to reduce hazards at work sites, improve quality and reduce the cost of
construction. However, there are many problems in the development of robots for the construction industry such as:
1. Large loads.
2. Components of variable sizes to be handled.
3. Adverse weather conditions such as variable humidity
and temperature.
4. Dust and dirt.
5. Need for three-dimensional movement.
6. Each site has a different size and shape.
Some of the robotic applications developed are
1. For inspection of interiors of pipes and drainage
conduits.
2. To detects voids around sewers and offshore pipes.
3. For excavation for slurry filled foundations.
4. Human-machine interface semi-automated earthmovers.
5. Concrete cutters and crushers to dismantle concrete
structures without creating noise and air pollution.
6. For plastering: An encouraging result has been
achieved in this area. Robots that can plaster 1.0 m2 area with 15 mm plaster
in only one minute have been developed. Manually the same work needs 30 minutes.
Sri. B. Srinivas Rao, associate professor, Department of Civil Engineering,
University College of Engg. Osmania Unversity, Hyderabad reports that for
external plastering of 15050 m2 area in 11 storey complex with 15 mm thick 1: 4
plaster total cost with robot plastering worked out Rs. 2,46,988 = 00 whereas
it would have cost Rs. 7,09,700 = 00 if conventional method was used. The whole
work was completed in 9 days only whereas conventional plastering would have
taken 54 days.
Lot of research and development is required to develop
robots for construction works since nowadays a good number of multistorey
buildings are coming up.
AUTOMATION IN DAM CONSTRUCTION
Dam construction is highly
mechanised. In earthen dam construction, heavy machinery are used for digging, transporting, placing and
consolidating required soil. Concreting is also highly mechanised.
AUTOMATION IN BRIDGE CONSTRUCTION
The modern trend in bridge
construction is to use precast construction. The superstructure of the bridge is cast in parts and erected on the site.
Noida bridge connecting
Delhi and Noida provides an eight-lane link of 552 m across river Yamuna. The
superstructure was cast in 13 spans of 42.5 m. The maximum weight of the precast
segment was 100 tonnes. Erection was done using launching truss.
JJ hospital flyover in
Mumbai is the most elegant and longest elevated road in India. For this casting, yard could be located 20 km away from the site. To facilitate transportation
and erection it was cast in several segments and connected at the site.
120m arch footbridge
across river Seonyce in Seoul, South Korea was built in six precast segments and
erected at the site. Ultra strength concrete (compressive strength 200 N/mm2) was
used for casting segments.
In Panvel Nadi viaduct
precast box girders were erected using launching girders and pushing the girder
by jacks.
AUTOMATION IN ROAD CONSTRUCTION
A number of machines are
used to mix, transport, place, compact and level the asphalt on superhighways.
Concreting is also mechanised in these constructions.
If you find
This information is helpful, please share it.
Thanks! For reading the article...
No comments:
Post a Comment