STAGES OF PLANNING
During the planning of a construction project, the entire project is phased out identifying the sequence of construction. Secondly
each phase is divided for operation into a number of jobs or units of
construction. Different stages of planning are as follows:
1. Job planning
2. Technical planning
3. Contract planning
JOB PLANNING
Each job or unit of construction has to be further
planned with respect to the following:
1. Manner of Execution of the Job
The jobs may be executed departmentally or through
contractors. In case the work is done through the contractor, the type of contract
is to be finalised.
2. Duration of the Job
The factors which contribute to the duration of job or
the proposed period of its completion is:
(i) Urgency of the work
(ii) Availability of resources
(iii) Position of the construction with reference to
network
3. Planning of Resources
Resources of a construction project comprise of the
following:
(i) Plant, equipment and machinery
(ii) Construction stores
(iii) Both technical and non-technical staff and skilled
and unskilled labour
(iv) Construction Material
TECHNICAL PLANNING
Technical planning is done by an engineer or concerned
authority for the economic execution of the construction project. It starts after
the administrative approval of the work is obtained for technical sanction.
Technical planning is carried out in order to satisfy the following objects:
(i) Finalisation of design, provide detailed drawing and
specification to be adopted.
(ii) Preparation of a detailed estimate and modification
of an estimate if necessary.
(iii) Deciding the executive authority, like departmentally
or through contract.
(iv) Planning resources and initiating procurement
action.
(v) Foresee the obstacles in the completion of the
project and take necessary steps for fruitful completion.
CONTRACT PLANNING
Contract planning is divided into the following two
categories:
1. Pre-tender planning
2. Post-tender planning
1. Pre-tender Planning
Planning required for the time of inviting of tenders up
to the receipt of the same is termed as pre-tender planning. It consists of the
following works:
(i)
Finalisation and Acquisition of Site
Before issue of order to contractors the acquisition of
the project site has to be finalised and legal issues if any should be
finalised.
(ii)
Planning of Resources
Resource planning includes the following:
(a) availability of site,
(b) availability of stores,
(c) availability of labour and
(d) availability of equipment and plants.
(iii)
Planning Time Limit
The requirement of resources and time limit are
inter-related and both these aspects are to be taken together. In some cases
the time needed for completion is decided based on the available resources.
Such is the case when the work has to be completed departmentally. Even when
the work has to be executed by the contractor, circumstances of the project has
to be decided and modified before inviting tenders. As a matter of fact the
contractor sub- mits tender considering the following aspects: (a) site survey,
(b) availability of materials,
(c) equipment and plants to be hired and purchased, (d)
fuel, (e) labour, (f) facilities for camp and (g) study of
drawing/design/specifications.
2. Post-tender Planning
In post-tender planning the
following aspects are considered irrespective of the work done by contractor or
departmentally: (a) setting campsite office, (b) welfare of staff/labour
amenities, (c) materials required, (d) labour required, (e) equipment, (f)
safety measures to avoid accidents and theft, (g) follow-up of
drawing/specifications and (h) billing, to record progress, to calculate
materials, labour, etc.
In the works executed by
contractors, responsibility is fixed for recording the work in the diary the
day-to-day details of work done. The planned progress in the form of bar charts
or progress reports should be known to the contractor as well as to the
engineer’s representative. It is normally the practice for all civil
engineering projects to make controlled construction stores available to the
contractor.
ADVANTAGES AND LIMITATIONS OF PLANNING
Following are the advantages and limitations of
planning:
1. Advantages
(i) Decision of network or bar chart makes the
contractor to know more about the job.
(ii) With proper planning, the financial burden will be
lessened for the contractor.
(iii) By proper programming, the weekly supply of labour can
be attended.
(iv) Programme provides a standard against which actual
work can be measured.
2. Limitations
(i) Effectiveness depends on correct assumptions.
(ii) Planning is expensive.
(iii) Planning delays action.
(iv) Planning encourages a false sense of activity.
SOURCE: BUILDING CONSTRUCTION MATERIALS AND TECHNIQUES | P. PURUSHOTHAMA RAJ
If you find
This information is helpful, please share it.
Thanks! For reading the article....
No comments:
Post a Comment