Formwork are temporary models in which concrete is poured and compressed to lay concrete according to the design. The formwork is set up in the correct position to cast the members onto the concrete structure. The formwork is held in place until the concrete hardens and gains strength.
Removing
the formwork is only recommended when the concrete has its dead weight and is
strengthened without the formwork or any props. Before dealing with the
precautionary measures to be taken when removing formwork or props, it is
always necessary to know the exact time to remove the formwork. The formwork
must be removed after the concrete structural elements supported in the
formwork have been removed. Here is a brief description of the exact time and
precautions to be taken to remove the formwork.
Correct Time of Removal of
Formwork
The time from which the
concrete is placed in formwork till the time the formwork is removed is called
as supporting period. This time period will vary, based on different factors
like:
TYPE AND GRADE OF
CONCRETE
• Type and grade of
concrete
• Admixtures used in
concrete mix
• Formwork designs
• Temperature
• Type of structural
element (Columns / beams / slabs)
• Quality of content
• Curing conditions
The
process of removing the formwork occurs after the concrete has turned and
gained sufficient strength, which is called formwork striking time. This can
cause stress on the structural dimension due to loss of support on or below all
sides, which is now the responsibility of a support structure. Properly
hardened concrete element can withstand these external stresses when removing
formwork. Formwork is left for a long time to aid in the healing process of
concrete components.
The
normal period for which the formwork can be removed in accordance with IS:
456-2000, Section 11 is shown below:
Strength of concrete vs. Structural Member
Type & Span for Formwork Removal
Concrete Strength |
Structural Member
Type and Span |
2.5
N/mm2 |
Lateral
parts of the formwork for all structural members can be removed |
70%
of design strength |
Interior
parts of formwork of slabs and beams with a span of up to 6m can be removed |
85%
of design strength |
Interior
parts of formwork of slabs and beams with a span of more than 6m can be
removed |
Formwork Stripping Time
(When Ordinary Portland Cement is used)
Type of Formwork |
Formwork Removal
Time |
Sides
of Walls, Columns and Vertical faces of beam |
24
hours to 48 hours (as per engineer’s decision) |
Slabs
(props left under) |
3
days |
Beam
soffits (props left under) |
7
days |
Removal of Props of Slabs: |
|
i)
Slabs spanning up to 4.5m |
14
days |
ii)
Slabs spanning over 4.5m |
14
days |
Removal of props for beams and arches |
|
i)
Span up to 6m |
14
days |
ii)
Span over 6m |
21
days |
Type
of Formwork |
Formwork
Removal Time |
Structured members are
structured based on designed loads. But before a structure is completed and
subjected to all the loads considered during structural design, the structural elements
will be subjected to its own weight and construction loads during the construction
process.
Therefore, in order to
proceed with construction activities at a rapid rate, it is necessary to
calculate the behavior of the structure under self-load and construction load.
This can be done and if the configuration member finds it safe, the formwork
can be removed.
If these calculations are
not possible, the following formula can be used to calculate safe formwork
strike times:
Characterization of the
cube of equal maturity to the structure required at the time of removal of the
formwork
= (Dead load +
Construction load) / ( total design load)
= Grade of concrete
This formula was presented
by Harrison (1995), which describes in detail the background that determines
the time it takes to remove the formwork.
Another method of
determining the strength of a concrete structure is to perform non-destructive
tests on the structural member.
Important Note:
It
should be noted that the time to remove the formwork shown above in Table-2 is
only when ordinary Portland cement is used.
Portland
Pozzolana cement is used in the normal construction process.
Therefore, the time shown in Table-2 should be modified.
For cement other than ordinary Portland
cement, the time required to remove the formwork is:
1.
Portland Pozzolana Cement – Removing time will be 10/7 of the time
specified above (Table-2)
2.
Low heat cement -
the transfer time is 10/7 of the time mentioned above (Table-2)
3.
Rapid Hardware
Cement - 3/7 of the time mentioned above (Table-2) The transfer time is
sufficient in all cases except the vertical sides of the slabs, beam and
columns, which must be maintained for 24 hours at least an hour.
Reference:
ACI (1995) In-place methods to estimate concrete
strength. ACI 228.1R-95.
ASTM (1987) Standard practice for estimating concrete
strength by the maturity method. ASTM C1074–87
BS 8110 - code of practice for the structural use of
concrete
IS-456 – Plain and Reinforced Concrete – Code of
Practice
What Happens If The Formwork Removed Early?
(A) Early Removal Of Side Support
if
you remove formwork immediately, the columns and beams sides may bulge if the
concrete has not hardened. And sides may
go out of plumb or line.
(B) Early Removal Of Support
If
you do not get enough strength, the system may be distracted or collapse.
Please note that if deviations occur at such times it will be permanent and
difficult to repair. So be careful.
Must
read: What
Is Beam | Uses | Types | Loads On Beam
If you find
This information helpful please share it.
Thanks! For reading the article.
No comments:
Post a Comment