IMPORTANCE
AND REQUIREMENT OF SURVEY | CHECKLIST OF SITE ENGINEER
The survey plays an important role in construction activities. The basic requirement is to ensure
proper location and alignment, including the height slope required for the
structure or overall layout of a plant. The survey is conducted to maintain the
above requirement. The following is a summary of the survey terms used:
SURVEYING: Surveying
is the art of making such measurements as will determine the relative positions
of points on the surface of the earth or on structure in order that the shape
and extent of any portions of the earth/structure may be ascertained and shown
on the map or plan.
LEVELING:
Levelling is the art of determining and representing the relative heights or
elevations of different points on the surface of the earth/structure.
SEQUENCE TO BE FOLLOWED
FOR THE SURVEY W.R.T. START OF THE WORK:
Following
are the salient points/ sequence of the survey to be followed for start of the project activates/ pour: -
WORK
IS DIVIDED IN TWO PARTS.
A. To
start a new project: Establishing of Main grid lines and Benchmark
with reference to known datum/reference to start in new work.
B. For
a pour in existing structure: Use of existing
reference/benchmark in the existing structure to define the location, alignment
and elevation of a pour.
USE OF SURVEY IN
VARIOUS DAY-TO-DAY ACTIVITIES OF CONSTRUCTION.
· Before we
deal with the uses of survey for various activities, the following steps are necessary
to carry out.
· Transfer
of reference line at each Building/floor to carry out checking of various
activities.
· Transferring
of BenchMark at each Building/floor.
· Above two
activities should be performed with great care and without any error, as the
effectiveness of total checking depends on these reference points.
· Establishing
layout of the building.
· Establishing
benchmark to check elevations of different floor etc.
· Use for
checking of formworks:
a)
Alignment checking
b)
Checking of verticality.
· Tolerance
for formwork
a)
Section dimension - ± 5 mm
b)
Plumb/ verticality - 5mm in 5 mtr. But
should not cumulative.
· Use in
checking of critical EPs.
a) Checking
of location
b)
Checking of elevation tolerance
c) Before
concreting ± 2 mm.
d) After
concreting ± 6mm.
e) Tolerance
on angle ± 0.500.
Survey is very important at
· Pre –
construction stage
· During
construction stage
· Post-construction
stage
Site Engineers must be
aware regarding requirement and importance of survey at pre-construction, during
construction and post-construction stages. Few of the requirements are detailed
below:
PRE-CONSTRUCTION SURVEY IS
REQUIRED FOR THE FOLLOWING:
1.
Defining the plant area in 20m X 20m plant
grid pattern with existing permanent reference.
2.
Location of various plant structures within
defined grid established as above.
3.
Making specific benchmark to take up the
work within building/structure.
4.
Marking and identification of a part of the
structure in various pours at various elevation w.r.t defined Benchmark /
reference.
5.
These marking are possible by:
· Theodolite.
· Measuring
tapes.
· Dumpy
level.
· Total
station.
6.
At the start of construction- usually the reference point is marked on reference pillars 2-3 meters away from the edge of
structure.
7.
After construction, it is transferred to
permanent structure and subsequently all reference to be taken from common
reference to avoid any cumulative error.
DURING CONSTRUCTION IS REQUIRED FOR THE
FOLLOWING:
1.
During construction, the survey is very
important. Following are the areas where a survey during construction requires by
supervisor/site engineers.
2.
Maintaining alignment of wall and position
of embedded part, pipe support/ piping sleeves etc.
3.
Maintaining the location of EP’s /
specifically critical EP’s.
4.
Maintaining the concrete top elevation of
plate EP’s / Critical EP’s.
5.
Maintaining the concrete top elevation
during finishing of green cutting.
6.
Maintaining the slopes of floors.
7.
Maintaining the levels of sumps.
8.
During concreting survey is made to ensure
the location of PVC water stop.
POST CONCRETE SURVEY IS REQUIRED FOR THE FOLLOWING:
1. Post the concrete survey is done for
all critical pours to ensure the final position of EP’s / Levels of concrete.
2. It is required to done to assess the
tolerance in alignment/level/pockets/bolts etc. in the concrete structure.
3. Post concrete survey is done to
examine the spot of honeycombed portion / visual observation of bulging and
type of surface finish in concrete.
If you find
This information helpful please share it.
Thanks! For reading the article.
No comments:
Post a Comment