What Is Form Work? | Types | Formwork Checklist | Removal Of The Formwork |
WHAT IS FORMWORK?
Formwork
is defined as a total system of support of fresh concrete to be placed it
includes:
1) Total
frame/mould of various shape in which concrete remain in contact.
2) Total
system of supporting arrangement i.e. by frame, pipes, acro-span, trusses etc.
3) Nuts,
bolts tie rods, bracing including other supporting systems for satisfactory
sustaining a load of concrete + live loads until the concrete attains the
strength to withstand the same
What Are The Various Type Of Formwork Are Used In
Construction?
CONVENTIONAL FORMWORK: Includes – formwork i.e. shuttering made up by steel plates and industrial plywood includes pipe support’s / wooden ball support.
DOCA FORMWORK: Specially designed formwork with simple methods for fixing in position and removing from the position. This tread name of formwork had proved confidence in various complicated structure for their satisfactory completion. This can be used for large slabs, big columns, deep beams, large size retaining walls, and hyperbolic cooling towers etc.
SLIP
FORMWORK: In a structure where shapes are regular of having a
uniform variation like shaft of the water tank, chimney, towers etc. and not having
penetrations. This type of formwork can effectively used for rapid construction
in this case formwork is design in such a way that it moves continuously ahead
to receive the fresh concrete in such a way that when it leaves the concrete
already placed should attain sufficient strength to withstand the load of
concrete + live load, while concreting is done. In this case concreting is done
continuously till the work is over for the shape
Example: The shaft of water tank for 15-20 Mtr. can be completed in 4 to 5 days.
JUMP
FORM: Where Shape / The geometry of the structure is not uniform and the height of the structure is more.
Jump formwork can be used. For example about 100 to 110 m high and 90m to 55 m
dia of cooling tower shell varying hyperbolically being constructed with the
jump form at RAPP-5&6 site.
Site Engineer / Supervisor Must Give
Attention To Following Areas While Checking The Formwork / Scaffolding.
PRE
CONSTRUCTION REQUIREMENT:
a) Alignment
level position of formwork w.r.t permanent reinforcement.
b) Type
of finish requirement decides the type of formwork.
c) Spacing
of the support system Tightening of bolt, tie rods etc.
d) Accuracy
of dimensions.
e) Gap
in the successive shutters to avoid slurry leakage.
f) Where
penetration / EP’s are to be made, the supports are to be re-ensured to maintain dimension, alignment
and level of the same.
g) Bracing
and adequate support for projections/ cantilever must be checked.
h) Wherever
construction joints are to be left, the position of shear keys, and support
arrangement to be ensured.
i) Safety
aspects to be taken care while checking the formwork the proper access to reach
other portion of the formwork to ensure, a case needs attention during the
concreting.
j) Form
fixing to be checked w.r.t removal of formwork point of view. It should be
easily removable without damaging the final concrete.
ALSO
READ: Know
the Difference between Formwork, Shuttering, Centering, and Staging
REQUIREMENT
DURING CONSTRUCTION
a) A
set of skilled carpenter to be ensured to attend the area immediately in case,
support’s / forms gets displaced while concreting / vibration of concrete.
b) Proper
illumination in internal and external location of pours to be ensured.
c) Application
of surface retarder immediately before the concreting where green cutting is
required.
POST
CONSTRUCTION REQUIREMENT:
a) In
general the codal practice for removing the formwork to be strictly followed
for removal of form.
b) For
special structures like dome of reactor and shell of Cooling Towers: -Specified
procedure to be followed for removal of form.
c) Specific
care to be observed for safety during disturbing.
d) Specific
care to be observed while removing formwork at high structure should not damage
the structure at floor.
ALSO
READ: Removal
of Concrete Formwork: Know the Correct Time | calculations | specification
Removal Of The Formwork At Various
Constructions Need Attention As Summarized Below
Forms should not be removed
until the concrete has achieved strength that is at least twice the stress to
which the concrete may be subjected at the time of removal of formwork.
However, under normal circumstances, where no significant variation in temperature
is seen the following striking period should be followed:
Removal
of forms and supports (As per IS456-2000)
Position of
formwork |
Min. period before
striking formwork. |
Vertical
formwork to Columns, walls, beams. |
16-24
hours |
Soffit
formwork to slabs (props left under after removal of formwork) |
3
days |
Soffit formwork of beams (props
left under after removal of formwork) |
7
days. |
Props
of slabs (spanning up to 4.5 m) |
7
days. |
Props
to slabs (span over 4.5 m) |
14
days. |
Props
to beams & arches (spanning up to 6) |
14
days. |
Props
to beams & arches (spanning over 6m) |
21
days. |
a) Striking
should be done slowly to avoid damage to projections and without shocks or
vibration.
b) When
forms are stripped, there should be no excessive deflection or distortion and
no evidence of damage to the concrete due to removal of support.
c) When
forms are removed before the specified curing is completed, curing should be
continued up to the specified time.
d) The
concrete supporting forms and shores not be removed from beams, floors and
walls until these structural units are strong enough to carry their own weight
or any approved superimposed load. In no case should supporting forms and
shores be removed from horizontal members before concrete strength has achieved
this specific concrete strength.
e) It
is always recommended to remove forms for columns and piers before forms for
beams and slabs
If you find
This information helpful please share it.
Thanks! For reading the article.
No comments:
Post a Comment